428 N HOMEWOOD ROAD 90049
Certificate Information: 428 N HOMEWOOD ROAD 90049
- Application / Permit
- 20010-20000-00929
- Plan Check / Job No.
- B20VN04687
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 20'-8" x 23'-6" OPEN TRELLIS PATIO COVER
- Permit Issued
- Issued on 11/25/2020
- Issuing Office
- Current Status
- CofO Issued on 6/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 11/4/2020 | SELLA BENYAMIN |
| Issued | 11/25/2020 | APPLICANT |
| CofO in Progress | 6/1/2023 | KEVIN SARGSYAN |
| Permit Finaled | 6/1/2023 | DANIEL ORRANTE |
| CofO Issued | 6/1/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/1/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 7/27/2020 | MITESH PATEL |
| Construction near power lines | Cleared | 10/22/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Clasico Construction; Lic. No.: 640521-B | 5112 REESE ROAD TORRANCE, CA 90505 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/10/2021 | Corrections Issued | JUAN VALENZUELA |
| Deputy Other (see comments) | 3/12/2021 | Conditional Approval | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 3/15/2021 | Approved | ROBERT SHELLY |
| Footing/Foundation/Slab | 3/23/2021 | Approved | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/28/2021 | Not Ready for Inspection | KENNETH NAGLE |
| Underground Mechanical | 5/5/2021 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 11/2/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/5/2022 | Conditional Approval | STEPHANIE SWANSON |
| FLOOD-Proofing Certificate | 12/5/2022 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/5/2022 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 12/5/2022 | Approved | STEPHANIE SWANSON |
| Insulation | 12/12/2022 | Corrections Issued | STEPHANIE SWANSON |
| Special/Order Compliance | 12/12/2022 | Partial Inspection | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 5/18/2023 | Approved | KEVIN SARGSYAN |
| Final | 5/18/2023 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 5/18/2023 | SGSOV Not Ready | KEVIN SARGSYAN |
| Service/Power Release | 5/18/2023 | Not Required | KEVIN SARGSYAN |
| Smoke Detectors | 5/18/2023 | Approved | KEVIN SARGSYAN |
| Final | 5/31/2023 | OK to Issue CofO | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 5/31/2023 | SGSOV Approved | KEVIN SARGSYAN |