14952 W POLK ST 91342
Certificate Information: 14952 W POLK ST 91342
- Application / Permit
- 20010-20000-00921
- Plan Check / Job No.
- B20VN04652
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 37' X 27'-2" 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A33. FIRE SPRINKLER REQUIRED NFPA-13D. "COMPLY WITH DEPARTMENT ORDER effective date 02/06/2008. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 5/15/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | SERGIO MUNIZ |
| Corrections Issued | 4/8/2020 | SERGIO MUNIZ |
| Quality Review Completed | 4/21/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 4/24/2020 | APPLICANT |
| Green Plans Picked Up | 7/2/2020 | APPLICANT |
| Applicant returned to address corrections | 7/28/2020 | SERGIO MUNIZ |
| Plan Check Approved | 9/18/2020 | SERGIO MUNIZ |
| Issued | 5/15/2023 | APPLICANT |
| CofO in Progress | 5/14/2025 | KEVIN BERBERYAN |
| Permit Finaled | 6/27/2025 | RUBEN SALAS |
| CofO Issued | 6/27/2025 | RUBEN SALAS |
| Permit Finaled | 6/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/26/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 5/28/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 7/1/2020 | SARAH YOUSSEF |
| Green Code | Cleared | 7/7/2020 | AARON COSTA |
| Hydrant and Access approval | Cleared | 7/13/2020 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 7/29/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gosen,, James W; Lic. No.: C43590 | 15315 BLEDSOE ST SYLMAR, CA 91342 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/12/2024 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 10/18/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Pre-Inspection | 10/18/2024 | Partial Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 10/18/2024 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 10/24/2024 | Approved | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 12/6/2024 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 12/12/2024 | Conditional Approval | KEVIN BERBERYAN |
| Green Building Rough | 12/12/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 12/12/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 12/12/2024 | Corrections Issued | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 12/12/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 12/20/2024 | Approved | MICHEL ABAJAN |
| Insulation | 12/30/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 12/30/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 1/13/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 1/13/2025 | Approved | KEVIN BERBERYAN |
| Shower Pan | 1/13/2025 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 1/30/2025 | Corrections Issued | KEVIN BERBERYAN |
| Sewer | 3/19/2025 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 3/19/2025 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 3/21/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 4/21/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 4/21/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 4/21/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 4/21/2025 | Approved | KEVIN BERBERYAN |
| Green Building Final | 4/21/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Final | 4/21/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Final | 4/21/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Not Ready | KEVIN BERBERYAN |
| Service/Power Release | 4/21/2025 | Not Required | KEVIN BERBERYAN |
| Smoke Detectors | 4/21/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Final | 4/25/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 4/25/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 4/25/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 4/29/2025 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Final | 4/29/2025 | Approved | KEVIN BERBERYAN |
| Final | 5/14/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 5/14/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 5/14/2025 | SGSOV No Gas | KEVIN BERBERYAN |
| Smoke Detectors | 5/14/2025 | Approved | KEVIN BERBERYAN |