7744 N VINELAND AVE 91352
Certificate Information: 7744 N VINELAND AVE 91352
- Application / Permit
- 20010-20000-00894
- Plan Check / Job No.
- B20VN04560
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 30' x 42' ADU PER LAMC 12.22 A 33 (c) & (d)
- Permit Issued
- Issued on 9/22/2020
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2020 | APPLICANT |
| Green Plans Picked Up | 4/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | CHON CHIO KUO |
| Corrections Issued | 4/20/2020 | CHON CHIO KUO |
| Quality Review Completed | 4/20/2020 | STEVEN KIM |
| Applicant returned to address corrections | 4/22/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/18/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/4/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 8/18/2020 | CHON CHIO KUO |
| Plan Check Approved | 9/9/2020 | CHON CHIO KUO |
| Issued | 9/22/2020 | APPLICANT |
| CofO in Progress | 12/22/2022 | MATTHEW NELSON |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/21/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 5/11/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 6/10/2020 | DAVID MATSON |
| Low Impact Development | Cleared | 7/10/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/10/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 7/22/2020 | KURT CORRAL |
Contact Information
| Contractor | Hudson Partners Construction Llc; Lic. No.: 1045535-B | 4605 LANKERSHIN BLVD STE 214 NORTH HOLLYWOOD, CA 91602 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/5/2021 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 3/23/2021 | Partial Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 3/24/2021 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 4/8/2021 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 4/8/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 4/8/2021 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 4/8/2021 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 4/8/2021 | Not Ready for Inspection | JOHN HAYES |
| Piling/Pier/Caisson | 4/14/2021 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 4/14/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 4/15/2021 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/24/2021 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 6/24/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 6/24/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 6/24/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 6/24/2021 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 6/24/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/8/2021 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 7/8/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 7/8/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/30/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 7/30/2021 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 7/30/2021 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 7/30/2021 | Approved | JOHN HAYES |
| Drywall Nailing | 8/11/2021 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 8/20/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 8/20/2021 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 8/25/2021 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 9/15/2021 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 12/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 12/15/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 12/15/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 12/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Final | 12/15/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 12/15/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 12/15/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 12/15/2021 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 12/15/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 12/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 2/2/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 2/2/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 2/2/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 2/2/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 2/18/2022 | Corrections Issued | MATT KELLERMAN |
| Final | 2/18/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Final | 2/18/2022 | Not Ready for Inspection | MATT KELLERMAN |
| HVAC-Final | 2/18/2022 | Not Ready for Inspection | MATT KELLERMAN |
| PLUMBING-Final | 2/18/2022 | Not Ready for Inspection | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 2/18/2022 | SGSOV Approved | MATT KELLERMAN |
| Service/Power Release | 2/18/2022 | Not Ready for Inspection | MATT KELLERMAN |
| ELECTRICAL-Final | 4/8/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/8/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 4/8/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/8/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/8/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 4/8/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 8/10/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 10/20/2022 | Partial Inspection | MATTHEW NELSON |
| Green Building Final | 10/20/2022 | Partial Inspection | MATTHEW NELSON |
| Service/Power Release | 10/20/2022 | Partial Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 12/7/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 12/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 12/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 12/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 12/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 12/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 12/21/2022 | Approved | MATTHEW NELSON |
| Final | 12/21/2022 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 12/21/2022 | Approved | MATTHEW NELSON |