307-307 1/2 W 89TH ST 90003
Certificate Information: 307-307 1/2 W 89TH ST 90003
- Application / Permit
- 20010-20000-00866
- Plan Check / Job No.
- B20VN04467
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX WITH ATTACHED GARAGE (BLDG B). FULLY SPRINKLERED.
- Permit Issued
- Issued on 2/3/2026
- Issuing Office
- Current Status
- Issued on 2/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | SAMUEL GONZALEZ |
| Green Plans Picked Up | 4/10/2020 | APPLICANT |
| Corrections Issued | 4/24/2020 | SAMUEL GONZALEZ |
| Quality Review Completed | 5/4/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 9/24/2020 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 3/2/2022 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 3/9/2022 | APPLICANT |
| Applicant returned to address corrections | 5/4/2022 | SAMUEL GONZALEZ |
| Plan Check Approved | 10/20/2025 | SAMUEL GONZALEZ |
| Issued | 2/3/2026 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 4/23/2020 | MICHAEL AYERS |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2020 | RENZ SORIANO |
| Address approval | Cleared | 1/14/2021 | RENZ SORIANO |
| Frnt yard landscape/Water mgmt | Cleared | 1/12/2022 | PABLO ESTRADA |
| Opn space landscape/Water mgmt | Cleared | 1/12/2022 | PABLO ESTRADA |
| Community Plan Implem. Overlay | Cleared | 2/9/2022 | ADALBERTO VERA |
| Community Plan Implem. Overlay | Cleared | 2/11/2022 | COLLINS ALLAN |
| Trees in Parkway | Cleared | 4/22/2022 | ADALBERTO VERA |
| Community Plan Implem. Overlay | Cleared | 6/10/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 7/4/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 7/8/2024 | ERNEST TSE |
| Community Plan Implem. Overlay | Cleared | 7/18/2024 | CELINA MORENO |
| Highway dedication | Cleared | 7/18/2024 | CELINA MORENO |
| Permit | Cleared | 7/18/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 7/18/2024 | CELINA MORENO |
| Sewer availability | Cleared | 7/18/2024 | CELINA MORENO |
| Community Plan Implem. Overlay | Cleared | 7/11/2025 | ANACANY HURTADO |
| Redevelopment Project Area | Cleared | 7/28/2025 | YASMINE BASHIRI |
Contact Information
| Contractor | R & M Real Estate Investments And Renovators Inc; Lic. No.: 1075969-B | 10910 LONG BEACH BLVD STE 103 LYNWOOD, CA 902622683 |
| Engineer | Jackson,, Calvin David; Lic. No.: C74896 | 14605 PAYNES CREEK RD RED BLUFF, CA 96080 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/27/2026 | Partial Approval | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 3/13/2026 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 3/13/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Deputy Reinf. Concrete | 3/17/2026 | Conditional Approval | ALEX COLIN |
| Deputy Wood Construction | 4/10/2026 | Conditional Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2026 | Approved | JOHN QUINTANILLA |
| Deputy Wood Construction | 4/24/2026 | Conditional Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2026 | Approved | JOHN QUINTANILLA |
| Deputy Wood Construction | 6/30/2026 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2026 | Conditional Approval | JOHN QUINTANILLA |