19243 W CALAHAN ST 91324
Certificate Information: 19243 W CALAHAN ST 91324
- Application / Permit
- 20010-20000-00864
- Plan Check / Job No.
- B20VN04433
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ADU PER 12.22 A33 (C) & (D)
- Permit Issued
- Issued on 8/31/2021
- Issuing Office
- Current Status
- CofO Issued on 11/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | STARR CHEN |
| Corrections Issued | 4/16/2020 | STARR CHEN |
| Quality Review Completed | 4/20/2020 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 4/27/2020 | APPLICANT |
| Building Plans Picked Up | 4/30/2020 | APPLICANT |
| Applicant returned to address corrections | 11/19/2020 | STARR CHEN |
| Applicant returned to address corrections | 1/14/2021 | STARR CHEN |
| Plan Check Approved | 2/5/2021 | STARR CHEN |
| No Progress | 3/22/2021 | STARR CHEN |
| Plan Check Approved | 8/13/2021 | STARR CHEN |
| Issued | 8/31/2021 | APPLICANT |
| CofO in Progress | 9/1/2022 | JEFFREY PARD |
| Permit Finaled | 11/21/2022 | JOHN JANSON |
| CofO Issued | 11/21/2022 | JOHN JANSON |
| Permit Finaled | 11/21/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/26/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/28/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2020 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 9/1/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/14/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 9/29/2020 | AARON COSTA |
| Hydrant and Access approval | Cleared | 3/25/2021 | KURT CORRAL |
| Construction near power lines | Cleared | 7/23/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
| Engineer | Mkrtchyan,, Gor; Lic. No.: L7387 | 16730 CANTLAY ST VAN NUYS, CA 91406 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/23/2021 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 11/23/2021 | Corrections Issued | JEFFREY PARD |
| Underground Mechanical | 12/6/2021 | Partial Approval | JEFFREY PARD |
| Wood Frame | 12/6/2021 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2021 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2021 | Partial Approval | JEFFREY PARD |
| ELECTRICAL-Rough | 2/2/2022 | Not Ready for Inspection | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2022 | Partial Approval | JEFFREY PARD |
| PLUMBING-Rough | 2/2/2022 | Not Ready for Inspection | JEFFREY PARD |
| Deputy Wood Construction | 2/4/2022 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 2/23/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 2/23/2022 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 2/23/2022 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 2/23/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 2/23/2022 | Not Ready for Inspection | JEFFREY PARD |
| Sewer | 2/23/2022 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 2/23/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/7/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 3/7/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 3/7/2022 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 3/7/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 3/7/2022 | Approved | JEFFREY PARD |
| Insulation | 3/30/2022 | Conditional Approval | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 3/30/2022 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 4/8/2022 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 4/8/2022 | Approved | JUSTIN HAWLEY |
| Insulation | 4/8/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 4/13/2022 | Not Ready for Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 4/15/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 4/15/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 5/12/2022 | Approved | JEFFREY PARD |
| Shower Pan | 5/12/2022 | Approved | JEFFREY PARD |
| Final | 7/28/2022 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 7/28/2022 | Approved | JEFFREY PARD |
| Green Building Final | 7/28/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Approved | JEFFREY PARD |
| Service/Power Release | 7/28/2022 | Approved | JEFFREY PARD |
| Smoke Detectors | 7/28/2022 | Approved | JEFFREY PARD |
| Final | 8/3/2022 | Corrections Issued | JEFFREY PARD |
| Final | 8/30/2022 | OK to Issue CofO | JEFFREY PARD |