19243 W CALAHAN ST 91324

Certificate Information: 19243 W CALAHAN ST 91324

Application / Permit
20010-20000-00864
Plan Check / Job No.
B20VN04433
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY ADU PER 12.22 A33 (C) & (D)
Permit Issued
Issued on 8/31/2021
Issuing Office
Current Status
CofO Issued on 11/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 STARR CHEN
Corrections Issued 4/16/2020 STARR CHEN
Quality Review Completed 4/20/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 4/27/2020 APPLICANT
Building Plans Picked Up 4/30/2020 APPLICANT
Applicant returned to address corrections 11/19/2020 STARR CHEN
Applicant returned to address corrections 1/14/2021 STARR CHEN
Plan Check Approved 2/5/2021 STARR CHEN
No Progress 3/22/2021 STARR CHEN
Plan Check Approved 8/13/2021 STARR CHEN
Issued 8/31/2021 APPLICANT
CofO in Progress 9/1/2022 JEFFREY PARD
Permit Finaled 11/21/2022 JOHN JANSON
CofO Issued 11/21/2022 JOHN JANSON
Permit Finaled 11/21/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/26/2020 GABRIEL ROBLES
Sewer availability Cleared 5/28/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/1/2020 GABRIEL ROBLES
Low Impact Development Cleared 9/1/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/14/2020 GABRIEL ROBLES
Green Code Cleared 9/29/2020 AARON COSTA
Hydrant and Access approval Cleared 3/25/2021 KURT CORRAL
Construction near power lines Cleared 7/23/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035
Engineer Mkrtchyan,, Gor; Lic. No.: L7387 16730 CANTLAY ST      VAN NUYS, CA 91406

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/23/2021 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 11/23/2021 Corrections Issued JEFFREY PARD
Underground Mechanical 12/6/2021 Partial Approval JEFFREY PARD
Wood Frame 12/6/2021 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 12/9/2021 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 2/2/2022 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 2/2/2022 Partial Approval JEFFREY PARD
PLUMBING-Rough 2/2/2022 Not Ready for Inspection JEFFREY PARD
Deputy Wood Construction 2/4/2022 Conditional Approval MORRIS JACKSON
BUILDING-Rough-Frame 2/23/2022 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 2/23/2022 Not Ready for Inspection JEFFREY PARD
Green Building Rough 2/23/2022 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 2/23/2022 Approved JEFFREY PARD
PLUMBING-Rough 2/23/2022 Not Ready for Inspection JEFFREY PARD
Sewer 2/23/2022 Approved JEFFREY PARD
Verify Sprinkler Sign Off 2/23/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 3/7/2022 Approved JEFFREY PARD
ELECTRICAL-Rough 3/7/2022 Approved JEFFREY PARD
Green Building Rough 3/7/2022 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 3/7/2022 Approved JEFFREY PARD
PLUMBING-Rough 3/7/2022 Approved JEFFREY PARD
Insulation 3/30/2022 Conditional Approval JUSTIN HAWLEY
Interior/Exterior Lathing 3/30/2022 Partial Approval JUSTIN HAWLEY
Drywall Nailing 4/8/2022 Approved JUSTIN HAWLEY
Green Building Rough 4/8/2022 Approved JUSTIN HAWLEY
Insulation 4/8/2022 Approved JUSTIN HAWLEY
Shower Pan 4/13/2022 Not Ready for Inspection JUSTIN HAWLEY
Interior/Exterior Lathing 4/15/2022 Approved JUSTIN HAWLEY
Shower Pan 4/15/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 5/12/2022 Approved JEFFREY PARD
Shower Pan 5/12/2022 Approved JEFFREY PARD
Final 7/28/2022 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 7/28/2022 Approved JEFFREY PARD
Green Building Final 7/28/2022 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 7/28/2022 SGSOV Approved JEFFREY PARD
Service/Power Release 7/28/2022 Approved JEFFREY PARD
Smoke Detectors 7/28/2022 Approved JEFFREY PARD
Final 8/3/2022 Corrections Issued JEFFREY PARD
Final 8/30/2022 OK to Issue CofO JEFFREY PARD