3676 N CROWNRIDGE DR 91403
Certificate Information: 3676 N CROWNRIDGE DR 91403
- Application / Permit
- 20010-20000-00852
- Plan Check / Job No.
- B20VN04387
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 116' X 64'6" 2-STORY SFD WITH ATTACHED THREE CAR GARAGE AND WITH 30' X 17'6" IRREGULAR SHAPED PATIO COVER AND WITH 69'6" X 41'6" IRREGULAR SHAPED BASEMENT , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING - SEE COMMENTS
- Permit Issued
- Issued on 2/9/2021
- Issuing Office
- Current Status
- CofO Issued on 5/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2020 | APPLICANT |
| Green Plans Picked Up | 3/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | RARES BODEA |
| Corrections Issued | 4/9/2020 | RARES BODEA |
| Quality Review Completed | 4/13/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 4/14/2020 | APPLICANT |
| Applicant returned to address corrections | 11/5/2020 | RARES BODEA |
| Applicant returned to address corrections | 12/17/2020 | RARES BODEA |
| Plan Check Approved | 2/9/2021 | RARES BODEA |
| Issued | 2/9/2021 | APPLICANT |
| CofO in Progress | 5/16/2023 | VINCENT HANLEY |
| Permit Finaled | 5/17/2023 | JOHN JANSON |
| CofO Issued | 5/17/2023 | JOHN JANSON |
| Permit Finaled | 5/17/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2020 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 4/29/2020 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 4/29/2020 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 4/29/2020 | GABRIEL ROBLES |
| Permit | Cleared | 4/30/2020 | GABRIEL ROBLES |
| Distance to fire station | Cleared | 5/4/2020 | JOHN CONNEALLY |
| Trees in Parkway | Cleared | 5/6/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 5/7/2020 | KURT CORRAL |
| BHO/Hillside ordinance | Cleared | 5/18/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 6/10/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/10/2020 | ADRIAN CASTRO |
| Green Code | Cleared | 6/12/2020 | MICHAEL AYERS |
| Low Impact Development | Cleared | 8/18/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 8/19/2020 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 12/17/2020 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 12/17/2020 | RARES BODEA |
| Excavation more than 5-ft deep | Cleared | 1/23/2021 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Montemayor,, G F; Lic. No.: C25258 | 1617 S WAVERLY GLEN WAY HACIENDA HEIGHTS, CA 91745 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
| Geologist | Kruger,, Mark Otto; Lic. No.: EG2345 | 10120 NATIONAL BLVD LOS ANGELES, CA 90034 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/14/2021 | Partial Approval | RONALD COWAN |
| Underground Mechanical | 5/14/2021 | Partial Approval | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 6/4/2021 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 6/4/2021 | Partial Approval | RONALD COWAN |
| Reinforced Concrete Frame | 7/6/2021 | Partial Approval | RONALD COWAN |
| Deputy Steel/Welding | 7/26/2021 | Approved | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 9/15/2021 | Partial Approval | RONALD COWAN |
| Piling/Pier/Caisson | 9/15/2021 | Partial Approval | RONALD COWAN |
| Deputy Reinf. Concrete | 9/16/2021 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 9/17/2021 | Approved | RONALD COWAN |
| Underground Mechanical | 10/1/2021 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 10/20/2021 | Partial Approval | RONALD COWAN |
| Deputy Reinf. Concrete | 10/22/2021 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 10/29/2021 | Approved | PETER FOLLING |
| Deputy Steel/Welding | 11/22/2021 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Partial Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2022 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2022 | Partial Approval | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2022 | No Access for Inspection | PETER FOLLING |
| PLUMBING-Rough | 5/10/2022 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 5/16/2022 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 5/25/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 5/27/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 5/27/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| MERV13>=Rough | 5/27/2022 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 5/27/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 6/10/2022 | Partial Approval | PETER FOLLING |
| Drywall Nailing | 6/14/2022 | Not Ready for Inspection | MORRIS JACKSON |
| Green Building Rough | 6/14/2022 | Not Ready for Inspection | MORRIS JACKSON |
| Shower Pan | 6/14/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/20/2022 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 6/23/2022 | Corrections Issued | VINCENT HANLEY |
| Drywall Nailing | 6/23/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/23/2022 | Approved | VINCENT HANLEY |
| HVAC-Final | 3/10/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/10/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 3/20/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/7/2023 | Approved | VINCENT HANLEY |
| Final | 4/7/2023 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 4/7/2023 | Approved | VINCENT HANLEY |
| MERV13>=Final | 4/7/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/7/2023 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 4/7/2023 | Approved | VINCENT HANLEY |
| Smoke Detectors | 4/7/2023 | Approved | VINCENT HANLEY |
| Final | 5/16/2023 | OK to Issue CofO | VINCENT HANLEY |