7115 W MACAPA DR 90068
Certificate Information: 7115 W MACAPA DR 90068
- Application / Permit
- 20010-20000-00840
- Plan Check / Job No.
- B20VN04336
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW DETACHED REC. ROOM/POOL BATH AND ATT. TRELLIS , FIRE SPRINKLERS MANDATORY
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2020 | APPLICANT |
| Green Plans Picked Up | 3/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 4/8/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 4/10/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 4/14/2020 | APPLICANT |
| Applicant returned to address corrections | 4/21/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 4/28/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 5/18/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 6/6/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 6/27/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 7/6/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 7/15/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 7/18/2022 | MOHAMMAD ESMAILI |
| Issued | 7/27/2022 | APPLICANT |
| CofO in Progress | 10/31/2022 | BRIAN SULLIVAN |
| Permit Finaled | 1/21/2023 | DEROLD HAUFF |
| CofO Issued | 1/21/2023 | DEROLD HAUFF |
| Permit Finaled | 1/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 4/27/2020 | TRACY WILLIAMS |
| Green Code | Cleared | 5/20/2020 | DAVID MATSON |
| Low Impact Development | Cleared | 6/18/2020 | MITESH PATEL |
| Hydrant and Access approval | Cleared | 6/25/2020 | KURT CORRAL |
| BHO/Hillside ordinance | Cleared | 6/30/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 6/30/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 6/30/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 6/30/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/30/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 9/4/2020 | TIMOTHY POWELL |
| GPI Written Notices | Cleared | 4/28/2022 | MOHAMMAD ESMAILI |
Contact Information
| Architect | Lopez,, Craig Joseph; Lic. No.: C14263 | 155 GRANADA ST STE "L" CAMARILLO, CA 93010 |
| Contractor | Owner-Builder | , |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/1/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/1/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 8/1/2022 | Partial Approval | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 8/3/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 8/23/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 8/23/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 8/23/2022 | Approved | BRIAN SULLIVAN |
| Wood Frame | 8/23/2022 | Partial Approval | BRIAN SULLIVAN |
| Insulation | 9/9/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 9/9/2022 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/24/2022 | Approved | BRIAN SULLIVAN |
| Final | 10/24/2022 | Conditional Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/24/2022 | Approved | BRIAN SULLIVAN |
| Green Building Final | 10/24/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 10/24/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 10/24/2022 | SGSOV Approved | BRIAN SULLIVAN |
| SUSMP-Std. Urban Storm Water | 10/24/2022 | Approved | BRIAN SULLIVAN |
| Service/Power Release | 10/24/2022 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 10/24/2022 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 10/24/2022 | Approved | BRIAN SULLIVAN |
| Final | 10/28/2022 | OK to Issue CofO | BRIAN SULLIVAN |