7115 W MACAPA DR 90068

Certificate Information: 7115 W MACAPA DR 90068

Application / Permit
20010-20000-00840
Plan Check / Job No.
B20VN04336
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW DETACHED REC. ROOM/POOL BATH AND ATT. TRELLIS , FIRE SPRINKLERS MANDATORY
Permit Issued
Issued on 7/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2020 APPLICANT
Green Plans Picked Up 3/27/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 MOHAMMAD ESMAILI
Corrections Issued 4/8/2020 MOHAMMAD ESMAILI
Quality Review Completed 4/10/2020 OMID HEDAYAT
Building Plans Picked Up 4/14/2020 APPLICANT
Applicant returned to address corrections 4/21/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 4/28/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 5/18/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 6/6/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 6/27/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 7/6/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 7/15/2022 MOHAMMAD ESMAILI
Plan Check Approved 7/18/2022 MOHAMMAD ESMAILI
Issued 7/27/2022 APPLICANT
CofO in Progress 10/31/2022 BRIAN SULLIVAN
Permit Finaled 1/21/2023 DEROLD HAUFF
CofO Issued 1/21/2023 DEROLD HAUFF
Permit Finaled 1/21/2023 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 4/27/2020 TRACY WILLIAMS
Green Code Cleared 5/20/2020 DAVID MATSON
Low Impact Development Cleared 6/18/2020 MITESH PATEL
Hydrant and Access approval Cleared 6/25/2020 KURT CORRAL
BHO/Hillside ordinance Cleared 6/30/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 6/30/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 6/30/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/30/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 6/30/2020 ADRIAN CASTRO
Sewer availability Cleared 6/30/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 9/4/2020 TIMOTHY POWELL
GPI Written Notices Cleared 4/28/2022 MOHAMMAD ESMAILI

Contact Information

Architect Lopez,, Craig Joseph; Lic. No.: C14263 155 GRANADA ST STE "L"      CAMARILLO, CA 93010
Contractor Owner-Builder       ,

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/1/2022 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 8/1/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 8/1/2022 Partial Approval BRIAN SULLIVAN
Piling/Pier/Caisson 8/3/2022 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 8/23/2022 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 8/23/2022 Approved BRIAN SULLIVAN
PLUMBING-Rough 8/23/2022 Approved BRIAN SULLIVAN
Wood Frame 8/23/2022 Partial Approval BRIAN SULLIVAN
Insulation 9/9/2022 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 9/9/2022 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 10/24/2022 Approved BRIAN SULLIVAN
Final 10/24/2022 Conditional Approval BRIAN SULLIVAN
Footing/Foundation/Slab 10/24/2022 Approved BRIAN SULLIVAN
Green Building Final 10/24/2022 Approved BRIAN SULLIVAN
Green Building Rough 10/24/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 10/24/2022 SGSOV Approved BRIAN SULLIVAN
SUSMP-Std. Urban Storm Water 10/24/2022 Approved BRIAN SULLIVAN
Service/Power Release 10/24/2022 Approved BRIAN SULLIVAN
Smoke Detectors 10/24/2022 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 10/24/2022 Approved BRIAN SULLIVAN
Final 10/28/2022 OK to Issue CofO BRIAN SULLIVAN