14157 W GAULT ST 91405

Certificate Information: 14157 W GAULT ST 91405

Application / Permit
20010-20000-00836
Plan Check / Job No.
B20VN04313
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
45' X 28'-3" NEW DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION.
Permit Issued
Issued on 6/22/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2020 APPLICANT
Green Plans Picked Up 3/27/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 SERGIO MUNIZ
Corrections Issued 4/7/2020 SERGIO MUNIZ
Quality Review Completed 4/16/2020 OMID HEDAYAT
Building Plans Picked Up 4/23/2020 APPLICANT
Plan Check Approved 6/21/2023 SERGIO MUNIZ
Plan Check Approved 6/21/2023 SERGIO MUNIZ
Issued 6/22/2023 APPLICANT
CofO in Progress 5/14/2024 RYAN SALAZAR
Permit Finaled 5/31/2024 RUBEN SALAS
CofO Issued 5/31/2024 RUBEN SALAS
Permit Finaled 5/31/2024 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/2/2020 JEREMY CARTER
Address approval Cleared 6/10/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 6/10/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 6/14/2021 ORVAL HERNANDEZ-MARCI
Construction near power lines Cleared 9/14/2021 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 3/17/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 2/6/2023 DAGOVERTO GUERRERO
Green Code Cleared 6/9/2023 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/1/2023 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Partial Approval RYAN SALAZAR
PLUMBING-Rough 9/25/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Approved RYAN SALAZAR
PLUMBING-Rough 10/20/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/30/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 10/30/2023 Approved RYAN SALAZAR
Green Building Rough 10/30/2023 Approved RYAN SALAZAR
HVAC-Rough 10/30/2023 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 10/30/2023 Approved RYAN SALAZAR
Insulation 11/9/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/9/2023 Partial Approval RYAN SALAZAR
Drywall Nailing 11/17/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/17/2023 Not Ready for Inspection RYAN SALAZAR
Shower Pan 11/17/2023 Approved RYAN SALAZAR
Sewer 12/11/2023 Approved RYAN SALAZAR
Underground Mechanical 1/2/2024 Approved RYAN SALAZAR
Pre-Inspection 3/26/2024 Partial Inspection RYAN SALAZAR
Final 4/26/2024 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 4/26/2024 Approved RYAN SALAZAR
Green Building Final 4/26/2024 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 4/26/2024 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 4/26/2024 Approved RYAN SALAZAR
Final 5/3/2024 Not Ready for Inspection RYAN SALAZAR
Green Building Final 5/3/2024 Approved RYAN SALAZAR
Service/Power Release 5/3/2024 Not Ready for Inspection RYAN SALAZAR
Final 5/13/2024 OK to Issue CofO RYAN SALAZAR
Service/Power Release 5/13/2024 Approved RYAN SALAZAR