6666 W 5TH ST 90048

Certificate Information: 6666 W 5TH ST 90048

Application / Permit
20010-20000-00816
Plan Check / Job No.
B20VN04217
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW FULLY SPRINKLERED IRREG SHAPED 70'-6" X 45'-6" TWO STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 6/12/2020
Issuing Office
Current Status
CofO Issued on 3/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2020 APPLICANT
Green Plans Picked Up 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/26/2020 JEROME MAGAT PALMA
Corrections Issued 4/3/2020 JEROME MAGAT PALMA
Quality Review Completed 4/3/2020 STEVEN KIM
Building Plans Picked Up 4/3/2020 APPLICANT
Plan Check Approved 6/12/2020 JEROME MAGAT PALMA
Issued 6/12/2020 APPLICANT
CofO in Progress 2/22/2021 EVAN COOPER
Permit Finaled 3/12/2021 KENNETH NAGLE
CofO Issued 3/12/2021 KENNETH NAGLE
Permit Finaled 3/12/2021 KENNETH NAGLE

Permit Application Clearance Information

CPC Cleared 4/27/2020 MIGUEL GAMBOA
ZI Cleared 4/27/2020 MIGUEL GAMBOA
Address approval Cleared 4/28/2020 EMIL KYUPELYAN
Permit Cleared 4/28/2020 EMIL KYUPELYAN
Frnt yard landscape/Water mgmt Cleared 4/29/2020 VINCENT QUITORIANO
Eng Process Fee Ord 176,300 Cleared 4/30/2020 EMIL KYUPELYAN
Trees in Parkway Cleared 5/6/2020 JOHN KIM
Green Code Cleared 5/13/2020 MICHAEL AYERS
Sewer availability Cleared 5/14/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 5/22/2020 KURT CORRAL
Low Impact Development Cleared 5/28/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/5/2020 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/24/2020 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/30/2020 Partial Approval EVAN COOPER
METHANE-Barrier 6/30/2020 Approved EVAN COOPER
METHANE-Subgrade 6/30/2020 Approved EVAN COOPER
Structural Steel Frame 7/8/2020 Partial Approval KENNETH NAGLE
PLUMBING-Rough 7/9/2020 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/14/2020 Partial Approval KENNETH NAGLE
PLUMBING-Rough 7/14/2020 Partial Approval KENNETH NAGLE
Insulation 7/15/2020 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 7/17/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/28/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/7/2020 Partial Approval EVAN COOPER
PLUMBING-Rough 8/24/2020 Approved EVAN COOPER
Special/Order Compliance 8/26/2020 Approved EVAN COOPER
Deputy Wood Construction 9/8/2020 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/9/2020 Partial Approval EVAN COOPER
HVAC-Rough 9/11/2020 Corrections Issued EVAN COOPER
HVAC-Rough 9/16/2020 Approved EVAN COOPER
Shower Pan 9/16/2020 Approved EVAN COOPER
ELECTRICAL-Rough 9/21/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 9/24/2020 Partial Inspection EVAN COOPER
Green Building Rough 9/24/2020 Not Ready for Inspection EVAN COOPER
METHANE-Rough 9/24/2020 Approved EVAN COOPER
Verify Sprinkler Sign Off 9/24/2020 Approved EVAN COOPER
Insulation 9/30/2020 Approved EVAN COOPER
Interior/Exterior Lathing 9/30/2020 Approved EVAN COOPER
Drywall Nailing 10/8/2020 Approved EVAN COOPER
Grounding or Bonding 12/8/2020 Partial Approval EVAN COOPER
ELECTRICAL-Final 1/28/2021 Approved EVAN COOPER
Gas Test 2/3/2021 Approved EVAN COOPER
PLUMBING-Final 2/3/2021 Approved EVAN COOPER
HVAC-Final 2/16/2021 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 2/17/2021 Approved EVAN COOPER
Final 2/17/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 2/17/2021 Approved EVAN COOPER
Green Building Final 2/17/2021 Approved EVAN COOPER
Green Building Rough 2/17/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/17/2021 SGSOV Approved EVAN COOPER
Service/Power Release 2/17/2021 Not Ready for Inspection EVAN COOPER
Smoke Detectors 2/17/2021 Approved EVAN COOPER
Final 2/22/2021 OK to Issue CofO EVAN COOPER
HVAC-Final 2/22/2021 Approved EVAN COOPER
Service/Power Release 2/22/2021 Approved EVAN COOPER