6666 W 5TH ST 90048
Certificate Information: 6666 W 5TH ST 90048
- Application / Permit
- 20010-20000-00816
- Plan Check / Job No.
- B20VN04217
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW FULLY SPRINKLERED IRREG SHAPED 70'-6" X 45'-6" TWO STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 6/12/2020
- Issuing Office
- Current Status
- CofO Issued on 3/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2020 | APPLICANT |
| Green Plans Picked Up | 3/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 4/3/2020 | JEROME MAGAT PALMA |
| Quality Review Completed | 4/3/2020 | STEVEN KIM |
| Building Plans Picked Up | 4/3/2020 | APPLICANT |
| Plan Check Approved | 6/12/2020 | JEROME MAGAT PALMA |
| Issued | 6/12/2020 | APPLICANT |
| CofO in Progress | 2/22/2021 | EVAN COOPER |
| Permit Finaled | 3/12/2021 | KENNETH NAGLE |
| CofO Issued | 3/12/2021 | KENNETH NAGLE |
| Permit Finaled | 3/12/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| CPC | Cleared | 4/27/2020 | MIGUEL GAMBOA |
| ZI | Cleared | 4/27/2020 | MIGUEL GAMBOA |
| Address approval | Cleared | 4/28/2020 | EMIL KYUPELYAN |
| Permit | Cleared | 4/28/2020 | EMIL KYUPELYAN |
| Frnt yard landscape/Water mgmt | Cleared | 4/29/2020 | VINCENT QUITORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2020 | EMIL KYUPELYAN |
| Trees in Parkway | Cleared | 5/6/2020 | JOHN KIM |
| Green Code | Cleared | 5/13/2020 | MICHAEL AYERS |
| Sewer availability | Cleared | 5/14/2020 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 5/22/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 5/28/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/5/2020 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/24/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 6/30/2020 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 6/30/2020 | Approved | EVAN COOPER |
| METHANE-Subgrade | 6/30/2020 | Approved | EVAN COOPER |
| Structural Steel Frame | 7/8/2020 | Partial Approval | KENNETH NAGLE |
| PLUMBING-Rough | 7/9/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/14/2020 | Partial Approval | KENNETH NAGLE |
| PLUMBING-Rough | 7/14/2020 | Partial Approval | KENNETH NAGLE |
| Insulation | 7/15/2020 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2020 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2020 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2020 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 8/24/2020 | Approved | EVAN COOPER |
| Special/Order Compliance | 8/26/2020 | Approved | EVAN COOPER |
| Deputy Wood Construction | 9/8/2020 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2020 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 9/11/2020 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 9/16/2020 | Approved | EVAN COOPER |
| Shower Pan | 9/16/2020 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 9/21/2020 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 9/24/2020 | Partial Inspection | EVAN COOPER |
| Green Building Rough | 9/24/2020 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 9/24/2020 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 9/24/2020 | Approved | EVAN COOPER |
| Insulation | 9/30/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/30/2020 | Approved | EVAN COOPER |
| Drywall Nailing | 10/8/2020 | Approved | EVAN COOPER |
| Grounding or Bonding | 12/8/2020 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Final | 1/28/2021 | Approved | EVAN COOPER |
| Gas Test | 2/3/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 2/3/2021 | Approved | EVAN COOPER |
| HVAC-Final | 2/16/2021 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 2/17/2021 | Approved | EVAN COOPER |
| Final | 2/17/2021 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 2/17/2021 | Approved | EVAN COOPER |
| Green Building Final | 2/17/2021 | Approved | EVAN COOPER |
| Green Building Rough | 2/17/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 2/17/2021 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 2/17/2021 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 2/17/2021 | Approved | EVAN COOPER |
| Final | 2/22/2021 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 2/22/2021 | Approved | EVAN COOPER |
| Service/Power Release | 2/22/2021 | Approved | EVAN COOPER |