18815 W HART ST 91335

Certificate Information: 18815 W HART ST 91335

Application / Permit
20010-20000-00813
Plan Check / Job No.
B20VN04198
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED ADU PER ORDINANCE.
Permit Issued
Issued on 9/24/2020
Issuing Office
Current Status
CofO Issued on 8/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 JESSE ARELLANO
Green Plans Picked Up 4/10/2020 APPLICANT
Corrections Issued 4/23/2020 JESSE ARELLANO
Quality Review Completed 4/29/2020 BILL STUTSMAN
Building Plans Picked Up 5/5/2020 APPLICANT
Applicant returned to address corrections 7/10/2020 JESSE ARELLANO
Plan Check Approved 9/10/2020 JESSE ARELLANO
Issued 9/24/2020 APPLICANT
CofO in Progress 4/4/2024 JEFFREY BULL
Permit Finaled 8/6/2024 JOHN JANSON
CofO Issued 8/6/2024 JOHN JANSON
Permit Finaled 8/6/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/24/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 5/18/2020 ABDULLAH SADOZAI
Sewer availability Cleared 5/18/2020 ABDULLAH SADOZAI
ZI Cleared 5/27/2020 MIGUEL GAMBOA
Hydrant and Access approval Cleared 6/3/2020 KURT CORRAL
Green Code Cleared 6/11/2020 MICHAEL AYERS
Low Impact Development Cleared 7/31/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 8/27/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/26/2023 Approved JEFFREY BULL
Underground Mechanical 9/22/2023 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 9/28/2023 Approved JEFFREY BULL
Deputy Wood Construction 10/11/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/11/2023 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/20/2023 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 10/24/2023 Approved JEFFREY BULL
PLUMBING-Rough 10/24/2023 Approved JEFFREY BULL
Underground Mechanical 10/30/2023 Approved JEFFREY BULL
Sewer 11/8/2023 Approved MORRIS JACKSON
Underground Mechanical 11/8/2023 Approved MORRIS JACKSON
Insulation 11/21/2023 Corrections Issued MORRIS JACKSON
Interior/Exterior Lathing 11/21/2023 Partial Approval MORRIS JACKSON
Shower Pan 11/21/2023 Approved MORRIS JACKSON
BUILDING-Rough-Frame 11/28/2023 Approved JEFFREY BULL
Green Building Rough 11/28/2023 Approved JEFFREY BULL
Verify Sprinkler Sign Off 11/28/2023 Approved JEFFREY BULL
Drywall Nailing 12/5/2023 Approved JEFFREY BULL
Final 3/19/2024 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 3/19/2024 Approved JEFFREY BULL
Green Building Final 3/19/2024 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Not Ready JEFFREY BULL
Service/Power Release 3/19/2024 Approved JEFFREY BULL
Smoke Detectors 3/19/2024 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Final 4/3/2024 Approved JEFFREY BULL
Final 4/3/2024 OK to Issue CofO JEFFREY BULL
Green Building Final 4/3/2024 Approved JEFFREY BULL
HVAC-Final 4/3/2024 Approved JEFFREY BULL
PLUMBING-Final 4/3/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 4/3/2024 SGSOV Approved JEFFREY BULL
Service/Power Release 4/3/2024 Not Required JEFFREY BULL
Smoke Detectors 4/3/2024 Approved JEFFREY BULL
Special/Order Compliance 4/10/2024 Corrections Issued JEFFREY BULL
Service/Power Release 5/15/2024 Approved JEFFREY BULL