8846 N TELFAIR AVE 91352

Certificate Information: 8846 N TELFAIR AVE 91352

Application / Permit
20010-20000-00792
Plan Check / Job No.
B20VN04059
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE 186481. All Work per Wood Frame Prescriptive Design.
Permit Issued
Issued on 1/20/2021
Issuing Office
Metro
Current Status
CofO Issued on 6/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 ZAW HAN
Corrections Issued 4/16/2020 ZAW HAN
Green Plans Picked Up 4/24/2020 APPLICANT
Quality Review Completed 4/29/2020 HERNAN ARREOLA
Plan Check Approved 12/30/2020 ZAW HAN
Issued 1/20/2021 APPLICANT
Building Plans Picked Up 1/21/2021 APPLICANT
CofO in Progress 5/20/2022 CHRISTOPHER DELLEFIELD
Permit Finaled 6/20/2022 DANIEL ORRANTE
CofO Issued 6/20/2022 DANIEL ORRANTE
Permit Finaled 6/20/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 5/3/2020 RIDWAN HARDY
Construction within easement Cleared 5/3/2020 RIDWAN HARDY
Address approval Cleared 8/28/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/28/2020 ADRIAN CASTRO
Sewer availability Cleared 8/28/2020 ADRIAN CASTRO
Green Code Cleared 10/27/2020 DAVID MATSON
Low Impact Development Cleared 11/12/2020 YVAINNE GALSIM
Clean Up Green Up Cleared 11/24/2020 RUBEN VASQUEZ
Roof/Waste drainage to street Cleared 11/24/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/10/2021 Partial Approval JOHN HAYES
Footing/Foundation/Slab 2/10/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 2/10/2021 Partial Approval JOHN HAYES
Footing/Foundation/Slab 2/22/2021 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 3/1/2021 Approved JOHN HAYES
BUILDING-Rough-Frame 5/10/2021 Corrections Issued JOHN HAYES
PLUMBING-Rough 5/10/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 5/25/2021 Approved JOHN HAYES
Wood Frame 5/25/2021 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 6/16/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 6/16/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 6/16/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/2/2021 Approved JOHN HAYES
Green Building Rough 7/2/2021 Approved JOHN HAYES
Interior/Exterior Lathing 7/2/2021 Partial Approval JOHN HAYES
MERV13>=Rough 7/2/2021 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 7/2/2021 Approved JOHN HAYES
Verify Sprinkler Sign Off 7/2/2021 Approved JOHN HAYES
Insulation 7/21/2021 Approved ALAN MORELOS
Shower Pan 7/21/2021 Approved ALAN MORELOS
Drywall Nailing 7/27/2021 No Access for Inspection ADAM ESCOTO
Drywall Nailing 7/29/2021 Not Ready for Inspection JOHN HAYES
Drywall Nailing 8/6/2021 Not Ready for Inspection JOHN HAYES
Drywall Nailing 8/11/2021 Approved JOHN HAYES
ELECTRICAL-Rough 8/26/2021 Not Ready for Inspection JOHN HAYES
Gas Test 8/26/2021 Not Ready for Inspection JOHN HAYES
Sewer 8/26/2021 Not Ready for Inspection JOHN HAYES
Gas Test 8/30/2021 Approved JOHN HAYES
Sewer 8/30/2021 Approved JOHN HAYES
Underground Mechanical 8/30/2021 Approved JOHN HAYES
Interior/Exterior Lathing 9/15/2021 Approved JUSTIN HAWLEY
Shower Pan 9/15/2021 Approved JUSTIN HAWLEY
Final 11/24/2021 Corrections Issued MATTHEW NELSON
Green Building Final 11/24/2021 Corrections Issued MATTHEW NELSON
MERV13>=Final 11/24/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 11/24/2021 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 11/24/2021 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 11/24/2021 Approved MATTHEW NELSON
ELECTRICAL-Final 12/16/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 12/16/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 12/16/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 12/16/2021 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 12/16/2021 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 12/16/2021 SGSOV Approved CHRISTOPHER DELLEFIELD
Service/Power Release 12/16/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 4/6/2022 Approved CHRISTOPHER DELLEFIELD
Final 4/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 4/6/2022 Approved CHRISTOPHER DELLEFIELD
Service/Power Release 4/6/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 5/20/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD
Service/Power Release 5/20/2022 Approved CHRISTOPHER DELLEFIELD