3330 W GLENHURST AVE 90039

Certificate Information: 3330 W GLENHURST AVE 90039

Application / Permit
20010-20000-00791
Plan Check / Job No.
B20VN04052
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW DETACHED 20' X 15' 1-CAR GARAGE. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 6/1/2020
Issuing Office
Current Status
CofO Issued on 12/18/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2020 APPLICANT
Assigned to Plan Check Engineer 3/6/2020 SARKIS HARABEDIAN
Corrections Issued 3/6/2020 SARKIS HARABEDIAN
Applicant returned to address corrections 4/28/2020 LUIS RINCON
Plan Check Approved 5/1/2020 GURUNATH NESARAJAH
Issued 6/1/2020 APPLICANT
CofO in Progress 12/17/2020 HAMIK HARTOUNIAN
Permit Finaled 12/18/2020 DEROLD HAUFF
CofO Issued 12/18/2020 DEROLD HAUFF
Permit Finaled 12/18/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/9/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 3/9/2020 CECILIO NAVARRO
Construction near power lines Cleared 4/23/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Shagirian,, Ashot; Lic. No.: C79415 11337 RUNNYMEDE ST      SUN VALLEY, CA 91352

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/3/2020 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/3/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/16/2020 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/16/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/29/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/29/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 7/16/2020 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/16/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/30/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/30/2020 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/30/2020 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 7/30/2020 Approved HAMIK HARTOUNIAN
Wood Frame 7/30/2020 Approved HAMIK HARTOUNIAN
Insulation 8/3/2020 Approved DAVID MATSON
Interior/Exterior Lathing 8/3/2020 Approved DAVID MATSON
Drywall Nailing 11/20/2020 Approved HAMIK HARTOUNIAN
Final 11/20/2020 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 11/20/2020 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/20/2020 SGSOV Not Required HAMIK HARTOUNIAN
Service/Power Release 11/20/2020 Approved HAMIK HARTOUNIAN
Smoke Detectors 11/20/2020 Approved HAMIK HARTOUNIAN
Final 12/17/2020 OK to Issue CofO HAMIK HARTOUNIAN