7742 N RADFORD AVE 91605
Certificate Information: 7742 N RADFORD AVE 91605
- Application / Permit
- 20010-20000-00787
- Plan Check / Job No.
- B20VN04031
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW Irregular 19'x37.5' two-story Accessory Dwelling Unit with a 4.5'x11.5' deck, and a 2.5'x5' patio cover.
- Permit Issued
- Issued on 9/8/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | LUIS RINCON |
| Corrections Issued | 3/25/2020 | LUIS RINCON |
| Quality Review Completed | 3/31/2020 | CHON CHIO KUO |
| Green Plans Picked Up | 6/15/2020 | APPLICANT |
| Applicant returned to address corrections | 12/21/2020 | LUIS RINCON |
| Applicant returned to address corrections | 2/11/2021 | LUIS RINCON |
| Applicant returned to address corrections | 5/7/2021 | LUIS RINCON |
| Applicant returned to address corrections | 6/3/2021 | LUIS RINCON |
| Applicant returned to address corrections | 9/17/2021 | LUIS RINCON |
| Applicant returned to address corrections | 11/22/2021 | LUIS RINCON |
| Plan Check Approved | 12/29/2021 | LUIS RINCON |
| Building Plans Picked Up | 1/4/2022 | APPLICANT |
| Issued | 9/8/2022 | APPLICANT |
| CofO in Progress | 3/28/2023 | MATTHEW NELSON |
| Permit Finaled | 1/17/2024 | RUBEN SALAS |
| CofO Issued | 1/17/2024 | RUBEN SALAS |
| Permit Finaled | 1/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2020 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 9/1/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 9/1/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 9/21/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 11/4/2020 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 11/10/2020 | GILBERT URREA |
| Sewer availability | Cleared | 11/30/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2021 | ADRIAN CASTRO |
| Hold | Cleared | 11/10/2022 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/12/2022 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 9/12/2022 | Partial Approval | CALEB MEISTER |
| Deputy Wood Construction | 11/14/2022 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 11/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 11/18/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 11/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 11/28/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 11/28/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/28/2022 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 11/28/2022 | Approved | MATTHEW NELSON |
| Insulation | 12/5/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/5/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 12/12/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 12/12/2022 | Approved | MATTHEW NELSON |
| Underground Mechanical | 1/31/2023 | Approved | MATTHEW NELSON |
| Final | 3/21/2023 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/21/2023 | Approved | MATTHEW NELSON |
| Green Building Final | 3/21/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/21/2023 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 3/21/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 3/21/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 3/28/2023 | Approved | MATTHEW NELSON |
| Final | 3/28/2023 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 3/28/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 3/28/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/28/2023 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 3/28/2023 | Approved | MATTHEW NELSON |