7036 N YOLANDA AVE 91335

Certificate Information: 7036 N YOLANDA AVE 91335

Application / Permit
20010-20000-00776
Plan Check / Job No.
B20VN03953
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW 24'-6" X 20'-0" FULLY SPRINKLERED ACCESSORY LIVING QUARTERS
Permit Issued
Issued on 2/19/2021
Issuing Office
Current Status
CofO Issued on 7/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 JEROME MAGAT PALMA
Corrections Issued 3/5/2020 JEROME MAGAT PALMA
Applicant returned to address corrections 1/6/2021 JEROME MAGAT PALMA
Plan Check Approved 2/1/2021 JEROME MAGAT PALMA
Issued 2/19/2021 APPLICANT
CofO in Progress 7/8/2021 VINCENT HANLEY
CofO Issued 7/13/2021 MICHAEL SMITH
Permit Finaled 7/13/2021 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/15/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/20/2021 ADRIAN CASTRO
Sewer availability Cleared 1/20/2021 ADRIAN CASTRO
ZI Cleared 1/20/2021 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/8/2021 Approved VINCENT HANLEY
PLUMBING-Rough 3/8/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/1/2021 Partial Approval VINCENT HANLEY
Green Building Rough 4/1/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 4/1/2021 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 4/1/2021 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 4/22/2021 Approved VINCENT HANLEY
Green Building Rough 4/22/2021 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 4/22/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 4/22/2021 Approved VINCENT HANLEY
Insulation 4/30/2021 Approved VINCENT HANLEY
Underground Mechanical 4/30/2021 Approved VINCENT HANLEY
Drywall Nailing 5/7/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/7/2021 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 5/19/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 6/11/2021 Approved VINCENT HANLEY
Final 6/11/2021 Corrections Issued VINCENT HANLEY
Gas Test 6/11/2021 Approved VINCENT HANLEY
Green Building Final 6/11/2021 Approved VINCENT HANLEY
HVAC-Final 6/11/2021 Approved VINCENT HANLEY
PLUMBING-Final 6/11/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/11/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 6/11/2021 Approved VINCENT HANLEY
Smoke Detectors 6/11/2021 Approved VINCENT HANLEY
Final 7/6/2021 Partial Inspection VINCENT HANLEY
Final 7/8/2021 OK to Issue CofO VINCENT HANLEY