14046 W CHAMBERLAIN ST 91340
Certificate Information: 14046 W CHAMBERLAIN ST 91340
- Application / Permit
- 20010-20000-00772
- Plan Check / Job No.
- B20VN03928
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 21' X 36' 1-STORY ACCESSORY DWELLING UNIT. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION. NFPA-13D SPRINKLER REQUIRED.
- Permit Issued
- Issued on 5/27/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2020 | APPLICANT |
| Green Plans Picked Up | 3/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | SERGIO MUNIZ |
| Corrections Issued | 3/23/2020 | SERGIO MUNIZ |
| Quality Review Completed | 3/27/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 3/31/2020 | APPLICANT |
| Applicant returned to address corrections | 4/23/2020 | SERGIO MUNIZ |
| Applicant returned to address corrections | 5/7/2020 | SERGIO MUNIZ |
| Plan Check Approved | 5/11/2020 | SERGIO MUNIZ |
| Issued | 5/27/2020 | LADBS |
| CofO in Progress | 5/11/2021 | JENNIFER RABUCHIN |
| CofO Issued | 11/6/2021 | MICHAEL SMITH |
| Permit Finaled | 11/6/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 4/7/2020 | ORVAL HERNANDEZ-MARCI |
| Address approval | Cleared | 4/8/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 4/8/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/8/2020 | ADRIAN CASTRO |
| Green Code | Cleared | 4/9/2020 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 4/10/2020 | GEORGE SUCHAND |
| Clean Up Green Up | Cleared | 5/8/2020 | JASON CHAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/12/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 6/16/2020 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 6/16/2020 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 6/16/2020 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/1/2020 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 7/1/2020 | Approved | JOHN HAYES |
| Insulation | 7/6/2020 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/6/2020 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2020 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 8/6/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Wood Frame | 8/6/2020 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 8/10/2020 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/28/2020 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 8/28/2020 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 8/28/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/28/2020 | Partial Approval | JENNIFER RABUCHIN |
| METHANE-Rough | 8/28/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/28/2020 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 8/28/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/31/2020 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 9/2/2020 | Approved | JENNIFER RABUCHIN |
| Sewer | 9/2/2020 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 9/10/2020 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 9/10/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/21/2020 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 9/21/2020 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/23/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/23/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 12/23/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 12/23/2020 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2020 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 12/23/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 12/23/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/22/2021 | Approved | JENNIFER RABUCHIN |
| Final | 2/22/2021 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 2/22/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/22/2021 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 2/22/2021 | Approved | JENNIFER RABUCHIN |
| Final | 5/12/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| Special/Order Compliance | 7/1/2021 | Approved | JENNIFER RABUCHIN |