6703 N RANCHITO AVE 91405

Certificate Information: 6703 N RANCHITO AVE 91405

Application / Permit
20010-20000-00764
Plan Check / Job No.
B20VN03847
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 44'-2" X 27'-10" ACCESSORY DWELLING UNIT W/ 3'-3" X 8'-0" PORCH PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 6/10/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2020 APPLICANT
Green Plans Picked Up 3/17/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 ARTIN ZARUKIAN
Corrections Issued 3/21/2020 ARTIN ZARUKIAN
Quality Review Completed 3/24/2020 STEVEN KIM
Building Plans Picked Up 4/7/2020 APPLICANT
Applicant returned to address corrections 1/12/2021 RAPHAEL ROSAS
Plan Check Approved 6/10/2024 ARTIN ZARUKIAN
Issued 6/10/2024 APPLICANT
CofO in Progress 1/5/2026 RYAN SALAZAR
Permit Finaled 1/9/2026 RUBEN SALAS
CofO Issued 1/9/2026 RUBEN SALAS
Permit Finaled 1/9/2026 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 5/6/2020 RIDWAN HARDY
Address approval Cleared 8/17/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 8/25/2020 GUILLERMO PETRA
Sewer availability Cleared 8/25/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 9/29/2020 MATTHEW CRAIG
Low Impact Development Cleared 4/12/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 4/13/2024 BRYAN GODINEZ
Green Code Cleared 5/26/2024 AARON COSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarians,, Harmick; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/19/2024 Approved RYAN SALAZAR
PLUMBING-Rough 12/2/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/3/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 12/27/2024 Approved RYAN SALAZAR
Sewer 12/27/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 1/17/2025 Conditional Approval RYAN SALAZAR
HVAC-Rough 1/17/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 1/17/2025 Partial Approval RYAN SALAZAR
Insulation 1/28/2025 Approved RYAN SALAZAR
Shower Pan 1/28/2025 Approved RYAN SALAZAR
Underground Mechanical 3/25/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/15/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 11/10/2025 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 11/10/2025 Corrections Issued MISAEL ESPARZA
Final 11/10/2025 Corrections Issued MISAEL ESPARZA
Green Building Final 11/10/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 11/10/2025 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/10/2025 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 11/10/2025 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 11/10/2025 Corrections Issued MISAEL ESPARZA
Verify Sprinkler Sign Off 11/10/2025 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 12/31/2025 Approved RYAN SALAZAR
Drywall Nailing 12/31/2025 Approved RYAN SALAZAR
Final 12/31/2025 OK to Issue CofO RYAN SALAZAR
Green Building Final 12/31/2025 Approved RYAN SALAZAR
Green Building Rough 12/31/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/31/2025 SGSOV Approved RYAN SALAZAR
Service/Power Release 12/31/2025 Approved RYAN SALAZAR
Smoke Detectors 12/31/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 12/31/2025 Approved RYAN SALAZAR