14929 W CORONA DEL MAR 90272

Certificate Information: 14929 W CORONA DEL MAR 90272

Application / Permit
20010-20000-00753
Plan Check / Job No.
B20VN03806
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 95' x 100' TWO-STORY SINGLE FAMILY DWELLING WITH HABITABLE BASEMENT AND ATTACHED 3-CAR GARAGE, AND ATTACHED TRELLIS. NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT
Permit Issued
Issued on 10/2/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 ALYSSA N NARCISO
Corrections Issued 3/24/2020 ALYSSA N NARCISO
Quality Review Completed 3/31/2020 CHON CHIO KUO
Building Plans Picked Up 4/1/2020 APPLICANT
Green Plans Picked Up 4/1/2020 APPLICANT
Applicant returned to address corrections 9/30/2020 SEAN SHAHMIRI
Applicant returned to address corrections 10/2/2020 SEAN SHAHMIRI
Plan Check Approved 10/2/2020 SEAN SHAHMIRI
Issued 10/2/2020 APPLICANT
CofO in Progress 11/3/2023 ARAM AVEDISIAN
Permit Finaled 11/18/2023 DANIEL ORRANTE
CofO Issued 11/18/2023 DANIEL ORRANTE
Permit Finaled 11/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Coastal Zone Cleared 4/8/2020 LAUREN PADICK
Miscellaneous Cleared 4/8/2020 LAUREN PADICK
Address approval Cleared 7/17/2020 CATHERINE ADROVER
Permit Cleared 7/17/2020 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 7/21/2020 CATHERINE ADROVER
Sewer availability Cleared 7/21/2020 CATHERINE ADROVER
Coastal Zone Cleared 8/4/2020 LAUREN PADICK
Coastal Zone Cleared 8/4/2020 LAUREN PADICK
Coastal Zone Cleared 8/4/2020 LAUREN PADICK
Miscellaneous Cleared 8/4/2020 LAUREN PADICK
Green Code Cleared 8/12/2020 AARON COSTA
Excavation more than 5-ft deep Cleared 8/24/2020 CALOSHA APPROVED
Disturb/Remove Protected Trees Cleared 9/2/2020 ALYSSA N NARCISO
Hydrant and Access approval Cleared 9/9/2020 MATTHEW CRAIG
Low Impact Development Cleared 9/9/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 9/10/2020 DINAH GARIN
Trees in Parkway Cleared 9/10/2020 JOHN KIM

Contact Information

Architect Azadi,, Bijan; Lic. No.: C18972 2825 PLAZA DEL AMO # 179      TORRANCE, CA 90503
Contractor A T H Construction; Lic. No.: 691539-B 18160 CHASE STREET      NORTHRIDGE, CA 91325
Engineer Vidal,, Juan Alonso; Lic. No.: GE861 7438 SHIRLEY AVE      RESEDA, CA 91335

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/6/2020 Approved ANDREW NAVE
Footing/Foundation/Slab 11/12/2020 Partial Approval ANDREW NAVE
PLUMBING-Rough 11/12/2020 Corrections Issued ANDREW NAVE
Excavation/Setback/Form/Re-Bar 12/4/2020 Partial Inspection ANDREW NAVE
Deputy Reinf. Concrete 12/11/2020 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 12/14/2020 Partial Approval ANDREW NAVE
PLUMBING-Rough 12/23/2020 Not Ready for Inspection PIERRE VEGA
Footing/Foundation/Slab 1/22/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 2/3/2021 Partial Approval ANDREW NAVE
Deputy Drilled-In Anchors 2/23/2021 Corrections Issued ROBERT SHELLY
Deputy Drilled-In Anchors 2/24/2021 Corrections Issued ROBERT SHELLY
Footing/Foundation/Slab 2/26/2021 Corrections Issued ANDREW NAVE
Deputy Wood Construction 3/9/2021 Approved ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 3/11/2021 Partial Approval ANDREW NAVE
Deputy Steel/Welding 3/31/2021 Approved ROBERT SHELLY
Deputy Wood Construction 4/5/2021 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 4/7/2021 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 4/28/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 6/16/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 6/21/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 6/25/2021 Partial Approval ANDREW NAVE
Deputy Wood Construction 7/2/2021 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 7/12/2021 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 8/10/2021 No Access for Inspection JOHN KIDWELL
Green Building Rough 8/10/2021 No Access for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 8/10/2021 No Access for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/11/2021 Approved ANDREW NAVE
Deputy Reinf. Concrete 9/21/2021 Partial Approval ANDREW NAVE
Deputy Drilled-In Anchors 10/21/2021 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 10/27/2021 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 12/8/2021 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 12/17/2021 Partial Approval ANDREW NAVE
PLUMBING-Rough 1/27/2022 Corrections Issued ANDREW NAVE
Sewer 1/27/2022 Approved ANDREW NAVE
PLUMBING-Rough 2/16/2022 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 2/23/2022 Partial Approval ANDREW NAVE
HVAC-Rough 2/28/2022 Approved ANDREW NAVE
PLUMBING-Rough 3/1/2022 Approved ANDREW NAVE
ELECTRICAL-Rough 3/2/2022 Approved ANDREW NAVE
BUILDING-Rough-Frame 3/3/2022 Approved ANDREW NAVE
Green Building Rough 3/3/2022 Approved ANDREW NAVE
Verify Sprinkler Sign Off 3/3/2022 Approved ANDREW NAVE
Insulation 3/10/2022 Corrections Issued ANDREW NAVE
Insulation 3/15/2022 Approved STEPHANIE SWANSON
Drywall Nailing 3/22/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 3/22/2022 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 3/25/2022 Partial Approval ANDREW NAVE
Shower Pan 3/25/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 4/1/2022 Partial Approval KRISTEN CAUSEY
Interior/Exterior Lathing 4/8/2022 Approved JOHN KIDWELL
Deputy Drilled-In Anchors 6/8/2022 Conditional Approval ANDREW NAVE
PLUMBING-Rough 1/27/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 1/31/2023 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 4/4/2023 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 6/8/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 6/13/2023 Approved GERMAN RODRIGUEZ MENDOZA
Rough-Elec/Plmb/HVAC 6/14/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 6/30/2023 Corrections Issued OGANES TARAKHCHYAN
HVAC-Final 7/3/2023 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 7/6/2023 Partial Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 7/20/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 7/27/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 8/8/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 8/17/2023 Corrections Issued EVAN COOPER
PLUMBING-Final 8/17/2023 Approved EVAN COOPER
Service/Power Release 9/12/2023 Approved KENNETH NAGLE
ELECTRICAL-Final 10/24/2023 Approved EVAN COOPER
HVAC-Final 10/27/2023 Approved ARAM AVEDISIAN
Final 11/3/2023 OK to Issue CofO ARAM AVEDISIAN
Footing/Foundation/Slab 11/3/2023 Approved ARAM AVEDISIAN
Green Building Final 11/3/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 11/3/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 11/3/2023 Approved ARAM AVEDISIAN