19209 W BESSEMER ST 91335
Certificate Information: 19209 W BESSEMER ST 91335
- Application / Permit
- 20010-20000-00744
- Plan Check / Job No.
- B20VN03782
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 21'-8" X 20'-0" DETACHED ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 6/4/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 3/22/2020 | JEROME MAGAT PALMA |
| Quality Review Completed | 3/25/2020 | ABDUL CHEGENI |
| Green Plans Picked Up | 3/26/2020 | APPLICANT |
| Plan Check Approved | 5/6/2020 | JEROME MAGAT PALMA |
| Issued | 6/4/2020 | LADBS |
| Building Plans Picked Up | 6/12/2020 | APPLICANT |
| CofO in Progress | 2/4/2021 | STEVEN BACK |
| Permit Finaled | 2/9/2021 | MICHAEL SMITH |
| CofO Issued | 2/9/2021 | MICHAEL SMITH |
| Permit Finaled | 2/9/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 4/14/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/14/2020 | ADRIAN CASTRO |
| ZI | Cleared | 4/14/2020 | MIGUEL GAMBOA |
| Construction near power lines | Cleared | 4/19/2020 | RIDWAN HARDY |
| Green Code | Cleared | 4/29/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/1/2020 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 7/1/2020 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 7/9/2020 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 7/9/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/23/2020 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 7/23/2020 | Approved | STEVEN BACK |
| Green Building Rough | 7/23/2020 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 7/23/2020 | Approved | STEVEN BACK |
| PLUMBING-Rough | 7/23/2020 | Approved | STEVEN BACK |
| Pre-Inspection | 7/24/2020 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 8/5/2020 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 8/5/2020 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2020 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 8/5/2020 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 8/5/2020 | Partial Approval | STEVEN BACK |
| Shower Pan | 8/5/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 8/10/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 8/10/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2020 | Approved | STEVEN BACK |
| Green Building Rough | 8/10/2020 | Approved | STEVEN BACK |
| Insulation | 8/10/2020 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 8/10/2020 | Approved | STEVEN BACK |
| Insulation | 8/13/2020 | Approved | STEVEN BACK |
| Drywall Nailing | 8/14/2020 | Approved | STEVEN BACK |
| Gas Test | 9/10/2020 | Not Ready for Inspection | STEVEN BACK |
| Sewer | 9/10/2020 | Approved | STEVEN BACK |
| Underground Mechanical | 9/10/2020 | Partial Approval | STEVEN BACK |
| Gas Test | 9/15/2020 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Final | 10/8/2020 | Corrections Issued | STEVEN BACK |
| Final | 10/8/2020 | Corrections Issued | STEVEN BACK |
| Green Building Final | 10/8/2020 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Final | 10/8/2020 | Corrections Issued | STEVEN BACK |
| PLUMBING-Final | 10/8/2020 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 10/8/2020 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 10/8/2020 | Approved | STEVEN BACK |
| Special/Order Compliance | 10/8/2020 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Final | 10/30/2020 | Not Ready for Inspection | STEVEN BACK |
| Final | 10/30/2020 | Corrections Issued | STEVEN BACK |
| Green Building Final | 10/30/2020 | Corrections Issued | STEVEN BACK |
| HVAC-Final | 10/30/2020 | Corrections Issued | STEVEN BACK |
| PLUMBING-Final | 10/30/2020 | Corrections Issued | STEVEN BACK |
| Service/Power Release | 10/30/2020 | Not Ready for Inspection | STEVEN BACK |
| Final | 12/2/2020 | Not Ready for Inspection | STEVEN BACK |
| Green Building Final | 12/2/2020 | Not Ready for Inspection | STEVEN BACK |
| Service/Power Release | 12/2/2020 | Not Ready for Inspection | STEVEN BACK |
| Final | 12/22/2020 | Corrections Issued | STEVEN BACK |
| Green Building Final | 12/22/2020 | Approved | STEVEN BACK |
| Service/Power Release | 12/22/2020 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Final | 12/31/2020 | No Access for Inspection | PAUL CHOPP |
| Final | 12/31/2020 | Corrections Issued | PAUL CHOPP |
| HVAC-Final | 12/31/2020 | No Access for Inspection | PAUL CHOPP |
| PLUMBING-Final | 12/31/2020 | No Access for Inspection | PAUL CHOPP |
| Service/Power Release | 12/31/2020 | No Access for Inspection | PAUL CHOPP |
| Final | 1/26/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Service/Power Release | 1/26/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 2/4/2021 | OK to Issue CofO | STEVEN BACK |
| Service/Power Release | 2/4/2021 | Approved | STEVEN BACK |