4162 S HOOPER AVE 90011

Certificate Information: 4162 S HOOPER AVE 90011

Application / Permit
20010-20000-00717
Plan Check / Job No.
B20VN03659
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT AND ATTACHED CARPORT FOR THE MAIN SFD IRR. SHAPE ( 33'-3"X29'-11") per LAMC 12.22 A.33(c)¹, (d)¹, and (g) "COMPLY WITH DEPARTMENT ORDER effective date 02/06/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 11/20/2020
Issuing Office
Current Status
CofO Issued on 3/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2020 APPLICANT
Green Plans Picked Up 3/10/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 MOHAMMAD ESMAILI
Corrections Issued 3/21/2020 MOHAMMAD ESMAILI
Quality Review Completed 3/27/2020 OMID HEDAYAT
Building Plans Picked Up 3/27/2020 APPLICANT
Applicant returned to address corrections 10/16/2020 MOHAMMAD ESMAILI
Plan Check Approved 11/20/2020 MOHAMMAD ESMAILI
Issued 11/20/2020 APPLICANT
CofO in Progress 3/22/2023 ANTHONY EGSON
CofO Issued 3/22/2023 DEROLD HAUFF
Permit Finaled 3/22/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/22/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 4/22/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 4/23/2020 EMIL KYUPELYAN
Sewer availability Cleared 4/23/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 6/8/2020 MATTHEW CRAIG
Low Impact Development Cleared 8/12/2020 ORVAL HERNANDEZ-MARCI
Green Code Cleared 9/11/2020 DAVID MATSON

Contact Information

Contractor Sire Energy Inc; Lic. No.: 1027415-B 21054 SHERMAN WAY #325      CANOGA PARK, CA 91303
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/16/2020 Approved FREDDIE RIVERA
Underground Mechanical 1/6/2021 Approved ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 1/8/2021 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 2/19/2021 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 2/19/2021 Partial Approval FREDDIE RIVERA
Green Building Rough 2/19/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 2/19/2021 Corrections Issued FREDDIE RIVERA
Underground Mechanical 2/19/2021 Not Ready for Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 2/19/2021 Approved FREDDIE RIVERA
Wood Frame 2/19/2021 Not Ready for Inspection FREDDIE RIVERA
Interior/Exterior Lathing 3/1/2021 Approved ROBERT MCDOWELL
PLUMBING-Rough 3/1/2021 Approved ROBERT MCDOWELL
Wood Frame 3/1/2021 Approved ROBERT MCDOWELL
Insulation 3/3/2021 No Access for Inspection KATHRYN BUTTERWORTH
Insulation 3/10/2021 Partial Approval FREDDIE RIVERA
Sewer 3/10/2021 Partial Approval FREDDIE RIVERA
Drywall Nailing 3/18/2021 Corrections Issued DAVID FEILER
Drywall Nailing 3/19/2021 Approved ROBERT MCDOWELL
Insulation 3/19/2021 Approved ROBERT MCDOWELL
Underground Mechanical 3/30/2021 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 8/13/2021 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 8/13/2021 Approved JOAQUIN GREENOUGH
Final 8/13/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/13/2021 Approved JOAQUIN GREENOUGH
Green Building Final 8/13/2021 Approved JOAQUIN GREENOUGH
Green Building Rough 8/13/2021 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/13/2021 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 8/13/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 8/13/2021 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Final 9/10/2021 No Access for Inspection ALAN MORELOS
Service/Power Release 9/10/2021 No Access for Inspection ALAN MORELOS
Special/Order Compliance 9/10/2021 Partial Approval ASHLEY THOMPSON
Final 3/23/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Service/Power Release 3/23/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 3/23/2022 Corrections Issued JOAQUIN GREENOUGH
Final 11/7/2022 Not Ready for Inspection ANTHONY EGSON
Service/Power Release 11/7/2022 Corrections Issued ANTHONY EGSON
Smoke Detectors 11/7/2022 Approved ANTHONY EGSON
Final 11/21/2022 Conditional Approval JULIAN AMAYA
Service/Power Release 11/21/2022 Approved JULIAN AMAYA
Final 3/22/2023 OK to Issue CofO ANTHONY EGSON