4162 S HOOPER AVE 90011
Certificate Information: 4162 S HOOPER AVE 90011
- Application / Permit
- 20010-20000-00717
- Plan Check / Job No.
- B20VN03659
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT AND ATTACHED CARPORT FOR THE MAIN SFD IRR. SHAPE ( 33'-3"X29'-11") per LAMC 12.22 A.33(c)¹, (d)¹, and (g) "COMPLY WITH DEPARTMENT ORDER effective date 02/06/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 11/20/2020
- Issuing Office
- Current Status
- CofO Issued on 3/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2020 | APPLICANT |
| Green Plans Picked Up | 3/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/21/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 3/27/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 3/27/2020 | APPLICANT |
| Applicant returned to address corrections | 10/16/2020 | MOHAMMAD ESMAILI |
| Plan Check Approved | 11/20/2020 | MOHAMMAD ESMAILI |
| Issued | 11/20/2020 | APPLICANT |
| CofO in Progress | 3/22/2023 | ANTHONY EGSON |
| CofO Issued | 3/22/2023 | DEROLD HAUFF |
| Permit Finaled | 3/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2020 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 4/22/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 4/23/2020 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 6/8/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 8/12/2020 | ORVAL HERNANDEZ-MARCI |
| Green Code | Cleared | 9/11/2020 | DAVID MATSON |
Contact Information
| Contractor | Sire Energy Inc; Lic. No.: 1027415-B | 21054 SHERMAN WAY #325 CANOGA PARK, CA 91303 |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/16/2020 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 1/6/2021 | Approved | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 1/8/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 2/19/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/19/2021 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 2/19/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 2/19/2021 | Corrections Issued | FREDDIE RIVERA |
| Underground Mechanical | 2/19/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 2/19/2021 | Approved | FREDDIE RIVERA |
| Wood Frame | 2/19/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/1/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 3/1/2021 | Approved | ROBERT MCDOWELL |
| Wood Frame | 3/1/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 3/3/2021 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Insulation | 3/10/2021 | Partial Approval | FREDDIE RIVERA |
| Sewer | 3/10/2021 | Partial Approval | FREDDIE RIVERA |
| Drywall Nailing | 3/18/2021 | Corrections Issued | DAVID FEILER |
| Drywall Nailing | 3/19/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 3/19/2021 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 3/30/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 8/13/2021 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 8/13/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 8/13/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/13/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 8/13/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 8/13/2021 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/13/2021 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 8/13/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 8/13/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 9/10/2021 | No Access for Inspection | ALAN MORELOS |
| Service/Power Release | 9/10/2021 | No Access for Inspection | ALAN MORELOS |
| Special/Order Compliance | 9/10/2021 | Partial Approval | ASHLEY THOMPSON |
| Final | 3/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 3/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 3/23/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 11/7/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 11/7/2022 | Corrections Issued | ANTHONY EGSON |
| Smoke Detectors | 11/7/2022 | Approved | ANTHONY EGSON |
| Final | 11/21/2022 | Conditional Approval | JULIAN AMAYA |
| Service/Power Release | 11/21/2022 | Approved | JULIAN AMAYA |
| Final | 3/22/2023 | OK to Issue CofO | ANTHONY EGSON |