12903 W KAMLOOPS ST 91331

Certificate Information: 12903 W KAMLOOPS ST 91331

Application / Permit
20010-20000-00711
Plan Check / Job No.
B20VN03613
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DET. ACCESSORRY DWELLING UNIT ( 21'-5"X25'-8") per LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 9/28/2020
Issuing Office
Current Status
CofO Issued on 3/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2020 APPLICANT
Green Plans Picked Up 3/10/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 MOHAMMAD ESMAILI
Corrections Issued 3/21/2020 MOHAMMAD ESMAILI
Quality Review Completed 3/27/2020 OMID HEDAYAT
Building Plans Picked Up 3/27/2020 APPLICANT
Plan Check Approved 9/28/2020 MOHAMMAD ESMAILI
Issued 9/28/2020 APPLICANT
CofO in Progress 12/7/2023 MICHEL ABAJAN
Permit Finaled 3/2/2024 RUBEN SALAS
CofO Issued 3/2/2024 RUBEN SALAS
Permit Finaled 3/2/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/22/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 4/22/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 4/23/2020 EMIL KYUPELYAN
Sewer availability Cleared 4/23/2020 EMIL KYUPELYAN
Green Code Cleared 6/11/2020 DAVID MATSON
Hydrant and Access approval Cleared 6/30/2020 KURT CORRAL
Low Impact Development Cleared 9/1/2020 ROBIN YAMADA

Contact Information

Contractor Sire Energy Construction; Lic. No.: 1027415-B 21054 SHERMAN WAY #325      CANOGA PARK, CA 91303
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/3/2021 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 12/17/2021 Corrections Issued MICHEL ABAJAN
METHANE-Barrier 12/17/2021 Approved MICHEL ABAJAN
METHANE-Subgrade 12/17/2021 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 2/5/2022 Corrections Issued CHARLES POWELL
Footing/Foundation/Slab 2/5/2022 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 2/6/2022 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 3/24/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 3/24/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 5/20/2022 No Access for Inspection MICHEL ABAJAN
Underground Mechanical 5/25/2022 No Access for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 No Access for Inspection MICHEL ABAJAN
Underground Mechanical 8/1/2022 No Access for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/2/2022 No Access for Inspection MICHEL ABAJAN
Insulation 9/2/2022 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 9/2/2022 No Access for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 9/8/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 9/8/2022 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 9/12/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 10/5/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 10/5/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/5/2022 Partial Approval MICHEL ABAJAN
Green Building Rough 10/5/2022 Approved MICHEL ABAJAN
HVAC-Rough 10/5/2022 Approved MICHEL ABAJAN
METHANE-Rough 10/5/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 10/5/2022 Approved MICHEL ABAJAN
Underground Mechanical 10/5/2022 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 10/5/2022 Approved MICHEL ABAJAN
Insulation 10/11/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/11/2022 Not Ready for Inspection MICHEL ABAJAN
Drywall Nailing 10/19/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/19/2022 Not Ready for Inspection MICHEL ABAJAN
Shower Pan 10/19/2022 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 11/1/2022 Partial Approval CALEB MEISTER
Shower Pan 11/1/2022 Approved CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 7/10/2023 SGSOV Not Ready MICHEL ABAJAN
ELECTRICAL-Final 7/21/2023 No Access for Inspection MICHEL ABAJAN
Final 7/21/2023 No Access for Inspection MICHEL ABAJAN
Green Building Final 7/21/2023 No Access for Inspection MICHEL ABAJAN
HVAC-Final 7/21/2023 No Access for Inspection MICHEL ABAJAN
PLUMBING-Final 7/21/2023 No Access for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 7/21/2023 No Access for Inspection MICHEL ABAJAN
Smoke Detectors 7/21/2023 No Access for Inspection MICHEL ABAJAN
Underground Mechanical 7/21/2023 No Access for Inspection MICHEL ABAJAN
ELECTRICAL-Final 9/7/2023 Not Ready for Inspection MICHEL ABAJAN
Final 9/7/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 9/7/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 9/7/2023 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Final 9/7/2023 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/7/2023 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 9/7/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 9/7/2023 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/7/2023 SGSOV Not Ready MICHEL ABAJAN
Final 11/27/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 11/27/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 11/27/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 11/27/2023 Approved MICHEL ABAJAN
Final 12/4/2023 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 12/4/2023 Approved MICHEL ABAJAN