7039 N DE CELIS PL 91406

Certificate Information: 7039 N DE CELIS PL 91406

Application / Permit
20010-20000-00709
Plan Check / Job No.
B20VN03606
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 37'-6" X 30'-6" IRREG SHAPED DETACHED ACCESSORY DWELLING UNIT
Permit Issued
Issued on 5/28/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 JEROME MAGAT PALMA
Corrections Issued 3/21/2020 JEROME MAGAT PALMA
Quality Review Completed 3/25/2020 ABDUL CHEGENI
Building Plans Picked Up 3/27/2020 APPLICANT
Green Plans Picked Up 3/31/2020 APPLICANT
Applicant returned to address corrections 5/20/2020 JEROME MAGAT PALMA
Plan Check Approved 5/20/2020 JEROME MAGAT PALMA
Issued 5/28/2020 LADBS
CofO in Progress 8/22/2020 MICHAEL TEMPLE
Permit Finaled 8/29/2020 MICHAEL SMITH
CofO Issued 8/29/2020 MICHAEL SMITH
Permit Finaled 8/29/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/21/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/21/2020 LEE GUILBEAUX
Sewer availability Cleared 4/21/2020 LEE GUILBEAUX
ZA Case Cleared 4/21/2020 LAUREN PADICK
Public Works-Highway Ded. Cleared 4/21/2020 LEE GUILBEAUX
Public Works-Sewers Cleared 4/21/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 4/28/2020 KURT CORRAL
Green Code Cleared 5/1/2020 MICHAEL AYERS
Low Impact Development Cleared 5/12/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 5/20/2020 GUILLERMO PETRA

Contact Information

Contractor Jerahian Araz; Lic. No.: 1045340-B 250 N COLLEGE PARK DR F36      UPLAND, CA 91786

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/2/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 6/9/2020 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 6/9/2020 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Partial Approval MICHEL ABAJAN
Green Building Rough 6/22/2020 Not Ready for Inspection MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 6/22/2020 Partial Approval MICHEL ABAJAN
Verify Sprinkler Sign Off 6/22/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/24/2020 Approved ROBERT MINASSIANS
ELECTRICAL-Rough 6/24/2020 Approved ROBERT MINASSIANS
Green Building Rough 6/24/2020 Approved ROBERT MINASSIANS
HVAC-Rough 6/24/2020 Approved ROBERT MINASSIANS
Interior/Exterior Lathing 6/24/2020 Approved ROBERT MINASSIANS
PLUMBING-Rough 6/24/2020 Approved ROBERT MINASSIANS
Insulation 6/29/2020 Approved MICHEL ABAJAN
Drywall Nailing 7/1/2020 Approved DANIEL DREW
Gas Test 7/22/2020 Approved DANIEL DREW
HVAC-Final 7/22/2020 Corrections Issued DANIEL DREW
PLUMBING-Final 7/22/2020 Approved DANIEL DREW
ELECTRICAL-Final 7/28/2020 Approved DANIEL DREW
Final 7/28/2020 Not Ready for Inspection DANIEL DREW
Footing/Foundation/Slab 7/28/2020 Approved DANIEL DREW
Green Building Final 7/28/2020 Not Ready for Inspection DANIEL DREW
HVAC-Final 7/28/2020 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 7/28/2020 SGSOV Approved DANIEL DREW
Service/Power Release 7/28/2020 Approved DANIEL DREW
Smoke Detectors 7/28/2020 Approved DANIEL DREW
Final 8/6/2020 Conditional Approval BEAU COLLINS
Green Building Final 8/6/2020 Approved BEAU COLLINS
Final 8/12/2020 OK to Issue CofO MICHAEL TEMPLE