9003 N GLADBECK AVE 91324
Certificate Information: 9003 N GLADBECK AVE 91324
- Application / Permit
- 20010-20000-00706
- Plan Check / Job No.
- B20VN03588
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (29'-3"x 19'-0") DETACHED ACCESSORY DWELLING UNIT. WORK PER ENGINEER.
- Permit Issued
- Issued on 7/16/2020
- Issuing Office
- Current Status
- CofO Issued on 11/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | TROY DEGUZMAN |
| Corrections Issued | 4/3/2020 | TROY DEGUZMAN |
| Quality Review Completed | 4/7/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 4/8/2020 | APPLICANT |
| Green Plans Picked Up | 4/8/2020 | APPLICANT |
| Plan Check Approved | 7/13/2020 | TROY DEGUZMAN |
| Issued | 7/16/2020 | APPLICANT |
| CofO in Progress | 11/22/2022 | DAVID SCANTLIN |
| Permit Finaled | 11/22/2022 | JOHN JANSON |
| CofO Issued | 11/22/2022 | JOHN JANSON |
| Permit Finaled | 11/22/2022 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/17/2020 | WALTER RAMIREZ |
| Green Code | Cleared | 4/17/2020 | AARON COSTA |
| Address approval | Cleared | 4/21/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/23/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 6/26/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/30/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rivera,, Bobby Zulueta; Lic. No.: C77218 | 14703 HELWIG AVE NORWALK, CA 90650 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/14/2020 | Partial Approval | JEFFREY PARD |
| Footing/Foundation/Slab | 12/22/2020 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 1/13/2021 | Approved | JEFFREY PARD |
| Underground Mechanical | 3/8/2021 | Approved | JEFFREY PARD |
| Rough-Elec/Plmb/HVAC | 3/30/2021 | Corrections Issued | JEFFREY PARD |
| BUILDING-Rough-Frame | 4/6/2021 | Partial Approval | JEFFREY PARD |
| ELECTRICAL-Rough | 4/6/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 4/6/2021 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 4/6/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 4/6/2021 | Approved | JEFFREY PARD |
| Rough-Elec/Plmb/HVAC | 4/6/2021 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 4/6/2021 | Not Ready for Inspection | JEFFREY PARD |
| Insulation | 4/21/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 4/21/2021 | Approved | JEFFREY PARD |
| Drywall Nailing | 5/7/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 5/7/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 5/7/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 11/4/2021 | Approved | JEFFREY PARD |
| Final | 11/4/2021 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 11/4/2021 | Corrections Issued | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 11/4/2021 | SGSOV Approved | JEFFREY PARD |
| Service/Power Release | 11/4/2021 | Not Ready for Inspection | JEFFREY PARD |
| Smoke Detectors | 11/4/2021 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 11/4/2021 | Approved | JEFFREY PARD |
| Final | 11/9/2021 | Partial Approval | JEFFREY PARD |
| Green Building Final | 11/9/2021 | Approved | JEFFREY PARD |
| Service/Power Release | 11/9/2021 | Approved | JEFFREY PARD |
| Final | 11/22/2022 | OK to Issue CofO | DAVID SCANTLIN |