5115 N ENCINO AVE 91316
Certificate Information: 5115 N ENCINO AVE 91316
- Application / Permit
- 20010-20000-00656
- Plan Check / Job No.
- B20VN03470
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD/GARAGE - 1 OF 3
- Permit Issued
- Issued on 8/12/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | CHON CHIO KUO |
| Corrections Issued | 3/16/2020 | CHON CHIO KUO |
| Quality Review Completed | 3/17/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 3/19/2020 | APPLICANT |
| Green Plans Picked Up | 5/8/2020 | APPLICANT |
| Applicant returned to address corrections | 6/8/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 7/14/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 8/11/2020 | CHON CHIO KUO |
| Plan Check Approved | 8/12/2020 | CHON CHIO KUO |
| Issued | 8/12/2020 | APPLICANT |
| CofO in Progress | 7/21/2021 | DAVID SANDOVAL |
| Permit Finaled | 7/22/2021 | JOHN JANSON |
| CofO Issued | 7/22/2021 | JOHN JANSON |
| Permit Finaled | 7/22/2021 | JOHN JANSON |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 3/19/2020 | JOHN KIM |
| Permit | Cleared | 4/2/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/2/2020 | LEE GUILBEAUX |
| ZA Case | Cleared | 4/7/2020 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/22/2020 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 5/5/2020 | KURT CORRAL |
| Green Code | Cleared | 5/19/2020 | MICHAEL AYERS |
| Low Impact Development | Cleared | 6/1/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/12/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/23/2020 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 9/23/2020 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 9/23/2020 | Partial Approval | STEVEN BACK |
| Deputy Wood Construction | 9/25/2020 | Approved | STEVEN BACK |
| Deputy Reinf. Concrete | 10/1/2020 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 10/2/2020 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 10/2/2020 | Approved | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 10/26/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2020 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 10/26/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2020 | Partial Approval | STEVEN BACK |
| Gas Test | 1/6/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 1/6/2021 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 1/19/2021 | Conditional Approval | BRENDAN LOONEY |
| HVAC-Rough | 1/19/2021 | Approved | BRENDAN LOONEY |
| Shower Pan | 1/19/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 1/25/2021 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 1/25/2021 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2021 | Corrections Issued | HENRY KIM |
| Green Building Rough | 1/25/2021 | Not Ready for Inspection | HENRY KIM |
| Shower Pan | 1/25/2021 | Approved | HENRY KIM |
| Verify Sprinkler Sign Off | 1/25/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 1/29/2021 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 1/29/2021 | Approved | HENRY KIM |
| Green Building Rough | 1/29/2021 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 1/29/2021 | Approved | HENRY KIM |
| Drywall Nailing | 2/5/2021 | Partial Approval | STEVEN BACK |
| Drywall Nailing | 2/9/2021 | Approved | STEVEN BACK |
| Insulation | 2/9/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 2/9/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 6/1/2021 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Final | 6/1/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Final | 6/1/2021 | Approved | STEVEN BACK |
| Service/Power Release | 6/1/2021 | Not Ready for Inspection | STEVEN BACK |
| Final | 7/13/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 7/13/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 7/13/2021 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 7/13/2021 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 7/13/2021 | Approved | STEVEN BACK |
| Final | 7/16/2021 | Not Ready for Inspection | STEVEN BACK |
| Service/Power Release | 7/16/2021 | Not Ready for Inspection | STEVEN BACK |
| Final | 7/20/2021 | OK to Issue CofO | DAVID SANDOVAL |
| Service/Power Release | 7/20/2021 | Approved | DAVID SANDOVAL |