4220 N ALLOTT AVE 91423
Certificate Information: 4220 N ALLOTT AVE 91423
- Application / Permit
- 20010-20000-00648
- Plan Check / Job No.
- B20VN03433
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE TWO STORY SFD WITH ATTACHED GARAGE _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D [SEE COMMENTS].
- Permit Issued
- Issued on 7/8/2020
- Issuing Office
- Current Status
- CofO Issued on 12/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | DAWN MC NULTY |
| Corrections Issued | 3/24/2020 | DAWN MC NULTY |
| Quality Review Completed | 3/24/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/25/2020 | APPLICANT |
| Green Plans Picked Up | 3/25/2020 | APPLICANT |
| Applicant returned to address corrections | 5/28/2020 | DAWN MC NULTY |
| Plan Check Approved | 7/8/2020 | DAWN MC NULTY |
| Issued | 7/8/2020 | APPLICANT |
| CofO in Progress | 8/18/2021 | ARAM AVEDISIAN |
| Permit Finaled | 12/18/2021 | MICHAEL SMITH |
| CofO Issued | 12/18/2021 | MICHAEL SMITH |
| Permit Finaled | 12/18/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/9/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 4/16/2020 | GEORGE SUCHAND |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2020 | CECILIO NAVARRO |
| Permit | Cleared | 4/22/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 4/22/2020 | CECILIO NAVARRO |
| Trees in Parkway | Cleared | 5/4/2020 | JOHN KIM |
| Green Code | Cleared | 5/5/2020 | MICHAEL AYERS |
| Low Impact Development | Cleared | 5/26/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/1/2020 | JOHN TRIANTAFYLLOS |
| GPI Written Notices | Cleared | 6/2/2020 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 6/2/2020 | DAWN MC NULTY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/23/2020 | Corrections Issued | CHARLES POWELL |
| Footing/Foundation/Slab | 7/31/2020 | No Access for Inspection | CHARLES POWELL |
| Footing/Foundation/Slab | 8/3/2020 | Partial Approval | CHARLES POWELL |
| Deputy Reinf. Concrete | 8/6/2020 | Approved | CHARLES POWELL |
| Deputy Steel/Welding | 8/6/2020 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 8/6/2020 | Approved | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2020 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2020 | Not Ready for Inspection | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2020 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 9/4/2020 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 9/14/2020 | Approved | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2020 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/7/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/7/2020 | Approved | ARAM AVEDISIAN |
| Gas Test | 10/7/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 10/7/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 10/7/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 10/7/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Wood Frame | 10/7/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/22/2020 | Approved | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2020 | Not Ready for Inspection | CHARLES POWELL |
| HVAC-Rough | 10/22/2020 | Approved | CHARLES POWELL |
| Shower Pan | 10/22/2020 | Approved | CHARLES POWELL |
| ELECTRICAL-Rough | 10/23/2020 | No Access for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 10/23/2020 | No Access for Inspection | ARAM AVEDISIAN |
| Wood Frame | 10/29/2020 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 11/5/2020 | Approved | ARAM AVEDISIAN |
| Insulation | 11/9/2020 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/9/2020 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 11/13/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 11/13/2020 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 11/23/2020 | Approved | ARAM AVEDISIAN |
| Pool Piping | 2/18/2021 | Not Ready for Inspection | CHARLES POWELL |
| BUILDING-Rough-Frame | 6/8/2021 | Approved | CHARLES POWELL |
| ELECTRICAL-Final | 6/8/2021 | Not Ready for Inspection | CHARLES POWELL |
| Green Building Final | 6/8/2021 | Not Ready for Inspection | CHARLES POWELL |
| HVAC-Final | 6/8/2021 | Not Ready for Inspection | CHARLES POWELL |
| PLUMBING-Final | 6/8/2021 | Not Ready for Inspection | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 6/8/2021 | SGSOV Not Ready | CHARLES POWELL |
| Smoke Detectors | 6/8/2021 | Not Ready for Inspection | CHARLES POWELL |
| Verify Sprinkler Sign Off | 6/8/2021 | Approved | CHARLES POWELL |
| ELECTRICAL-Final | 6/14/2021 | Partial Approval | CHARLES POWELL |
| PLUMBING-Final | 6/14/2021 | Approved | CHARLES POWELL |
| Final | 6/22/2021 | Corrections Issued | CHARLES POWELL |
| Green Building Final | 6/22/2021 | Approved | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 6/22/2021 | SGSOV Approved | CHARLES POWELL |
| Service/Power Release | 6/22/2021 | Not Ready for Inspection | CHARLES POWELL |
| Smoke Detectors | 6/22/2021 | Approved | CHARLES POWELL |
| Final | 8/18/2021 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 8/18/2021 | Approved | ARAM AVEDISIAN |