4900 N RUBIO AVE 91436

Certificate Information: 4900 N RUBIO AVE 91436

Application / Permit
20010-20000-00624
Plan Check / Job No.
B20VN03296
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
New 13'-9" x 16'-8" detached patio cover with a direct vent fireplace per engineer
Permit Issued
Issued on 5/20/2020
Issuing Office
Current Status
CofO Issued on 11/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2020 APPLICANT
Green Plans Picked Up 3/5/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 ANGELICA DAVE
Corrections Issued 3/17/2020 ANGELICA DAVE
Quality Review Completed 3/18/2020 CHON CHIO KUO
Building Plans Picked Up 3/19/2020 APPLICANT
Applicant returned to address corrections 4/8/2020 ANGELICA DAVE
Plan Check Approved 5/20/2020 ANGELICA MARTINEZ
Issued 5/20/2020 APPLICANT
CofO in Progress 11/19/2020 RONALD COWAN
CofO Issued 11/23/2020 MICHAEL SMITH
Permit Finaled 11/23/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/23/2020 ELAINE LEI
Green Code Cleared 4/28/2020 MICHAEL AYERS
Low Impact Development Cleared 5/15/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/15/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: C38991 25531 PRADO DELASBELLOTAS      CALABASAS, CA 91302

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 5/26/2020 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 5/26/2020 Approved RONALD COWAN
Footing/Foundation/Slab 5/26/2020 Partial Approval RONALD COWAN
Footing/Foundation/Slab 5/29/2020 Approved RONALD COWAN
BUILDING-Rough-Frame 7/6/2020 Corrections Issued RONALD COWAN
Green Building Rough 7/6/2020 Approved RONALD COWAN
Interior/Exterior Lathing 7/6/2020 Partial Approval RONALD COWAN
Verify Sprinkler Sign Off 7/6/2020 Corrections Issued RONALD COWAN
BUILDING-Rough-Frame 7/15/2020 Not Ready for Inspection MICHAEL TEMPLE
Insulation 7/15/2020 Not Ready for Inspection MICHAEL TEMPLE
Interior/Exterior Lathing 7/15/2020 Corrections Issued MICHAEL TEMPLE
Verify Sprinkler Sign Off 7/15/2020 Not Ready for Inspection MICHAEL TEMPLE
BUILDING-Rough-Frame 7/20/2020 Approved RONALD COWAN
Interior/Exterior Lathing 7/20/2020 Approved RONALD COWAN
Verify Sprinkler Sign Off 7/20/2020 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 10/14/2020 SGSOV Not Ready RONALD COWAN
Final 10/21/2020 Corrections Issued RONALD COWAN
Green Building Final 10/21/2020 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 10/21/2020 SGSOV Approved RONALD COWAN
Service/Power Release 10/21/2020 Approved RONALD COWAN
Smoke Detectors 10/21/2020 Approved RONALD COWAN
Final 10/30/2020 Corrections Issued RONALD COWAN
Final 11/12/2020 OK to Issue CofO RONALD COWAN