4900 N RUBIO AVE 91436
Certificate Information: 4900 N RUBIO AVE 91436
- Application / Permit
- 20010-20000-00623
- Plan Check / Job No.
- B20VN03296
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story, 74' x 52'-8" single-family dwelling with attached 2-car garage per engineer. NFPA-13D fire sprinklered throughout.
- Permit Issued
- Issued on 5/21/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2020 | APPLICANT |
| Green Plans Picked Up | 3/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | ANGELICA DAVE |
| Corrections Issued | 3/17/2020 | ANGELICA DAVE |
| Quality Review Completed | 3/18/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/19/2020 | APPLICANT |
| Applicant returned to address corrections | 4/8/2020 | ANGELICA DAVE |
| Plan Check Approved | 5/20/2020 | ANGELICA MARTINEZ |
| Issued | 5/21/2020 | LADBS |
| CofO in Progress | 11/17/2020 | PETER FOLLING |
| Permit Finaled | 11/17/2020 | MICHAEL SMITH |
| CofO Issued | 11/17/2020 | MICHAEL SMITH |
| Permit Finaled | 11/17/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2020 | ELAINE LEI |
| Permit | Cleared | 4/23/2020 | ELAINE LEI |
| Sewer availability | Cleared | 4/23/2020 | ELAINE LEI |
| Green Code | Cleared | 4/28/2020 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 5/6/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 5/15/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/15/2020 | ADRIAN CASTRO |
| Trees in Parkway | Cleared | 5/20/2020 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: C38991 | 25531 PRADO DELASBELLOTAS CALABASAS, CA 91302 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/22/2020 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 5/26/2020 | Approved | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 5/26/2020 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 5/26/2020 | Partial Approval | RONALD COWAN |
| Underground Mechanical | 5/26/2020 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 5/29/2020 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2020 | Partial Approval | RONALD COWAN |
| HVAC-Rough | 6/26/2020 | Approved | RONALD COWAN |
| PLUMBING-Rough | 6/26/2020 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 7/2/2020 | Not Ready for Inspection | RONALD COWAN |
| ELECTRICAL-Rough | 7/2/2020 | Approved | RONALD COWAN |
| Green Building Rough | 7/2/2020 | Not Ready for Inspection | RONALD COWAN |
| Verify Sprinkler Sign Off | 7/2/2020 | Not Ready for Inspection | RONALD COWAN |
| Interior/Exterior Lathing | 7/6/2020 | Partial Approval | RONALD COWAN |
| BUILDING-Rough-Frame | 7/15/2020 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Rough | 7/15/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Insulation | 7/15/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 7/15/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Verify Sprinkler Sign Off | 7/15/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 7/20/2020 | Approved | RONALD COWAN |
| Green Building Rough | 7/20/2020 | Approved | RONALD COWAN |
| Insulation | 7/20/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 7/20/2020 | Partial Approval | RONALD COWAN |
| Verify Sprinkler Sign Off | 7/20/2020 | Approved | RONALD COWAN |
| Drywall Nailing | 7/23/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 7/23/2020 | Approved | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 10/14/2020 | SGSOV Not Ready | RONALD COWAN |
| Final | 10/21/2020 | Corrections Issued | RONALD COWAN |
| Green Building Final | 10/21/2020 | Approved | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 10/21/2020 | SGSOV Approved | RONALD COWAN |
| Service/Power Release | 10/21/2020 | Approved | RONALD COWAN |
| Smoke Detectors | 10/21/2020 | Approved | RONALD COWAN |
| Final | 10/30/2020 | Corrections Issued | RONALD COWAN |
| Final | 11/12/2020 | OK to Issue CofO | RONALD COWAN |