10930 N RALSTON AVE 91331
Certificate Information: 10930 N RALSTON AVE 91331
- Application / Permit
- 20010-20000-00622
- Plan Check / Job No.
- B20VN03295
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 23'-0 X 35'-6" 3-CAR GARAGE W/ IRREGULAR 27'-0" X 35'-6" ACCESSORY DWELLING UNIT ON SECOND FLOOR PER LAMC 12.22.A.33(C) AND (D). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Current Status
- CofO Issued on 4/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2020 | APPLICANT |
| Green Plans Picked Up | 3/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | JENNIFER LEE |
| Corrections Issued | 4/3/2020 | JENNIFER LEE |
| Quality Review Completed | 4/7/2020 | STEVEN KIM |
| Applicant returned to address corrections | 3/31/2021 | JENNIFER LEE |
| Building Plans Picked Up | 4/1/2021 | APPLICANT |
| Plan Check Approved | 5/24/2021 | JENNIFER LEE |
| Issued | 5/25/2021 | APPLICANT |
| CofO in Progress | 10/4/2024 | MICHEL ABAJAN |
| No Progress | 11/27/2024 | ROBERT GOLD |
| CofO in Progress | 11/27/2024 | ROBERT GOLD |
| CofO in Progress | 11/27/2024 | ROBERT GOLD |
| CofO Issued | 4/16/2026 | RUBEN SALAS |
| Permit Finaled | 4/16/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2020 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 8/6/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/6/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 8/12/2020 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 9/9/2020 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 9/30/2020 | JOHN KIM |
| Low Impact Development | Cleared | 2/8/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/9/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ruvalcaba,, Martin Eduardo; Lic. No.: C75838 | 5942 AUTRY AVE LAKEWOOD, CA 90712 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/18/2021 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 10/18/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/21/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/24/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Barrier | 10/24/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 10/24/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/28/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/3/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Partial Approval | MICHEL ABAJAN |
| METHANE-Rough | 2/9/2023 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 2/9/2023 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/8/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/8/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/8/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/8/2023 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 3/8/2023 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 3/10/2023 | Conditional Approval | JUAN VALENZUELA |
| Insulation | 3/24/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/24/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Drywall Nailing | 7/3/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/3/2023 | Approved | MICHEL ABAJAN |
| Final | 7/3/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/3/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/3/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/3/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 7/3/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 7/3/2023 | Approved | MICHEL ABAJAN |
| Final | 7/24/2023 | Corrections Issued | MICHEL ABAJAN |
| Service/Power Release | 7/24/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 8/21/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 8/21/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 10/4/2024 | OK to Issue CofO | MICHEL ABAJAN |
| Special/Order Compliance | 10/10/2024 | Corrections Issued | MICHEL ABAJAN |