4048-4050 N CONTERA ROAD 91436
Certificate Information: 4048-4050 N CONTERA ROAD 91436
- Application / Permit
- 20010-20000-00621
- Plan Check / Job No.
- B20VN03289
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD WITH ATTACHED GARAGE AND ATTACHED ACCESSORY DWELLING UNIT (849 SF) PER LAMC 12.22 A.33 (c) and (e)
- Permit Issued
- Issued on 12/17/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2020 | APPLICANT |
| Green Plans Picked Up | 3/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | CHON CHIO KUO |
| Corrections Issued | 3/16/2020 | CHON CHIO KUO |
| Quality Review Completed | 3/17/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 3/17/2020 | APPLICANT |
| Applicant returned to address corrections | 11/9/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 11/18/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 12/2/2020 | CHON CHIO KUO |
| Plan Check Approved | 12/15/2020 | CHON CHIO KUO |
| Issued | 12/17/2020 | APPLICANT |
| CofO in Progress | 5/6/2022 | VINCENT HANLEY |
| CofO Issued | 5/9/2022 | MICHAEL SMITH |
| Permit Finaled | 5/9/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/28/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 10/8/2020 | MITESH PATEL |
| Green Code | Cleared | 10/14/2020 | MICHAEL AYERS |
| Address approval | Cleared | 10/20/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 10/20/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 10/20/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 10/20/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2020 | LEE GUILBEAUX |
| Permit | Cleared | 10/20/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/20/2020 | LEE GUILBEAUX |
| Work Adjacent to Public Way | Cleared | 10/20/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/20/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 10/22/2020 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/21/2020 | Approved | DONALD SUNSERI |
| Footing/Foundation/Slab | 1/15/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2021 | Partial Approval | RONALD COWAN |
| Deputy Wood Construction | 3/8/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2021 | Partial Approval | RONALD COWAN |
| PLUMBING-Rough | 3/17/2021 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 4/14/2021 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/20/2021 | Approved | RONALD COWAN |
| HVAC-Rough | 4/20/2021 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 4/29/2021 | Partial Approval | RONALD COWAN |
| Shower Pan | 4/29/2021 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 5/6/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 5/6/2021 | Approved | DAVID SANDOVAL |
| Insulation | 5/6/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 5/6/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 5/6/2021 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 5/17/2021 | Approved | RONALD COWAN |
| Gas Test | 9/10/2021 | Approved | RONALD COWAN |
| ELECTRICAL-Final | 2/17/2022 | Approved | VINCENT HANLEY |
| HVAC-Final | 2/17/2022 | Approved | VINCENT HANLEY |
| Gas Test | 2/25/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/25/2022 | Approved | VINCENT HANLEY |
| Final | 3/22/2022 | Partial Approval | VINCENT HANLEY |
| Green Building Final | 3/22/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/22/2022 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 3/22/2022 | Approved | VINCENT HANLEY |
| Smoke Detectors | 3/22/2022 | Approved | VINCENT HANLEY |
| Service/Power Release | 3/29/2022 | Approved | VINCENT HANLEY |
| Final | 5/6/2022 | OK to Issue CofO | VINCENT HANLEY |
| Service/Power Release | 5/6/2022 | Approved | VINCENT HANLEY |