13549 W HART ST 91405
Certificate Information: 13549 W HART ST 91405
- Application / Permit
- 20010-20000-00608
- Plan Check / Job No.
- B20VN03232
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ACCESSORY DWELLING UNIT (34'6"x18'-9") and TWO CAR GARAGE ( 21'-0"x 20'-6")
- Permit Issued
- Issued on 7/23/2021
- Issuing Office
- Current Status
- CofO Issued on 3/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | MOHAMMAD ESMAILI |
| Green Plans Picked Up | 3/27/2020 | APPLICANT |
| Corrections Issued | 3/31/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 4/16/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 4/23/2020 | APPLICANT |
| Plan Check Approved | 7/15/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 7/21/2021 | MOHAMMAD ESMAILI |
| Issued | 7/23/2021 | APPLICANT |
| CofO in Progress | 1/5/2023 | CHRISTOPHER DELLEFIELD |
| No Progress | 1/6/2023 | ROBERT GOLD |
| CofO in Progress | 3/23/2023 | MICHAEL SMITH |
| Permit Finaled | 3/31/2023 | RONALD MYRICK |
| CofO Issued | 3/31/2023 | RONALD MYRICK |
| Permit Finaled | 3/31/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 5/8/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/8/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 7/29/2020 | KURT CORRAL |
| Green Code | Cleared | 8/11/2020 | MICHAEL AYERS |
| Low Impact Development | Cleared | 8/19/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 8/25/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 9/10/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/18/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Underground Mechanical | 8/19/2021 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/23/2021 | Approved | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 8/26/2021 | Conditional Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2021 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/10/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 1/10/2022 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 1/10/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 1/10/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 1/10/2022 | Approved | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 1/10/2022 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 1/10/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/13/2022 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 1/13/2022 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 1/24/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 1/24/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 2/23/2022 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 3/22/2022 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 4/1/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 4/21/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Shower Pan | 4/21/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 4/26/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/28/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/2/2022 | Corrections Issued | JORDAN KUTZLY |
| Green Building Final | 12/2/2022 | Not Ready for Inspection | JORDAN KUTZLY |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Approved | JORDAN KUTZLY |
| Service/Power Release | 12/2/2022 | Not Ready for Inspection | JORDAN KUTZLY |
| Smoke Detectors | 12/2/2022 | Not Ready for Inspection | JORDAN KUTZLY |
| Final | 12/9/2022 | Corrections Issued | JORDAN KUTZLY |
| Green Building Final | 12/9/2022 | Approved | JORDAN KUTZLY |
| Service/Power Release | 12/9/2022 | Approved | JORDAN KUTZLY |
| Smoke Detectors | 12/9/2022 | Approved | JORDAN KUTZLY |
| Final | 1/5/2023 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |