13549 W HART ST 91405

Certificate Information: 13549 W HART ST 91405

Application / Permit
20010-20000-00608
Plan Check / Job No.
B20VN03232
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ACCESSORY DWELLING UNIT (34'6"x18'-9") and TWO CAR GARAGE ( 21'-0"x 20'-6")
Permit Issued
Issued on 7/23/2021
Issuing Office
Current Status
CofO Issued on 3/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2020 APPLICANT
Assigned to Plan Check Engineer 3/26/2020 MOHAMMAD ESMAILI
Green Plans Picked Up 3/27/2020 APPLICANT
Corrections Issued 3/31/2020 MOHAMMAD ESMAILI
Quality Review Completed 4/16/2020 OMID HEDAYAT
Building Plans Picked Up 4/23/2020 APPLICANT
Plan Check Approved 7/15/2021 MOHAMMAD ESMAILI
Plan Check Approved 7/21/2021 MOHAMMAD ESMAILI
Issued 7/23/2021 APPLICANT
CofO in Progress 1/5/2023 CHRISTOPHER DELLEFIELD
No Progress 1/6/2023 ROBERT GOLD
CofO in Progress 3/23/2023 MICHAEL SMITH
Permit Finaled 3/31/2023 RONALD MYRICK
CofO Issued 3/31/2023 RONALD MYRICK
Permit Finaled 3/31/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 5/8/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/8/2020 ADRIAN CASTRO
Sewer availability Cleared 5/8/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 7/29/2020 KURT CORRAL
Green Code Cleared 8/11/2020 MICHAEL AYERS
Low Impact Development Cleared 8/19/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 8/25/2020 ADRIAN CASTRO
Construction near power lines Cleared 9/10/2020 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/18/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Underground Mechanical 8/19/2021 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 8/23/2021 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 8/26/2021 Conditional Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/10/2022 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/10/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 1/10/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 1/10/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 1/10/2022 Approved CHRISTOPHE COCHRAN
Rough-Elec/Plmb/HVAC 1/10/2022 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 1/10/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/13/2022 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 1/13/2022 Approved CHRISTOPHE COCHRAN
Insulation 1/24/2022 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 1/24/2022 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 2/23/2022 Partial Approval ASHLEY THOMPSON
Insulation 3/22/2022 Approved CHRISTOPHE COCHRAN
Drywall Nailing 4/1/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 4/21/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Shower Pan 4/21/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 4/26/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/28/2022 Approved CHRISTOPHE COCHRAN
Final 12/2/2022 Corrections Issued JORDAN KUTZLY
Green Building Final 12/2/2022 Not Ready for Inspection JORDAN KUTZLY
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Approved JORDAN KUTZLY
Service/Power Release 12/2/2022 Not Ready for Inspection JORDAN KUTZLY
Smoke Detectors 12/2/2022 Not Ready for Inspection JORDAN KUTZLY
Final 12/9/2022 Corrections Issued JORDAN KUTZLY
Green Building Final 12/9/2022 Approved JORDAN KUTZLY
Service/Power Release 12/9/2022 Approved JORDAN KUTZLY
Smoke Detectors 12/9/2022 Approved JORDAN KUTZLY
Final 1/5/2023 OK to Issue CofO CHRISTOPHER DELLEFIELD