11309 N ENCINO AVE 91344

Certificate Information: 11309 N ENCINO AVE 91344

Application / Permit
20010-20000-00578
Plan Check / Job No.
B20VN03148
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'-6" x 32' ONE-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 3/9/2021
Issuing Office
Current Status
CofO Issued on 4/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 SEAN SHAHMIRI
Green Plans Picked Up 3/20/2020 APPLICANT
Corrections Issued 3/26/2020 SEAN SHAHMIRI
Quality Review Completed 4/6/2020 OMID HEDAYAT
Building Plans Picked Up 4/9/2020 APPLICANT
Plan Check Approved 3/9/2021 SEAN SHAHMIRI
Issued 3/9/2021 APPLICANT
Applicant returned to address corrections 3/15/2021 SEAN SHAHMIRI
CofO in Progress 4/3/2024 DAVID SCANTLIN
Permit Finaled 4/8/2024 JOHN JANSON
CofO Issued 4/8/2024 JOHN JANSON
Permit Finaled 4/8/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/27/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 4/28/2020 GUILLERMO PETRA
Sewer availability Cleared 4/28/2020 GUILLERMO PETRA
ZI Cleared 4/28/2020 HERMINIGILDO AGUSTIN
ZI Cleared 4/28/2020 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 5/29/2020 VASIL MIHALEV
Low Impact Development Cleared 11/19/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/6/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 2/23/2021 MATTHEW CRAIG
Green Code Cleared 2/26/2021 AARON COSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/26/2021 Approved DAVID SCANTLIN
Underground Mechanical 4/26/2021 Approved DAVID SCANTLIN
Footing/Foundation/Slab 4/30/2021 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 5/11/2021 Approved DAVID SCANTLIN
ELECTRICAL-Rough 5/27/2021 Approved DAVID SCANTLIN
HVAC-Rough 5/27/2021 Approved DAVID SCANTLIN
Gas Test 6/4/2021 Partial Approval DAVID SCANTLIN
Insulation 6/4/2021 Partial Approval DAVID SCANTLIN
Drywall Nailing 6/10/2021 Approved DAVID SCANTLIN
Green Building Rough 6/10/2021 Approved DAVID SCANTLIN
Interior/Exterior Lathing 6/16/2021 Partial Approval KRISTEN CAUSEY
Shower Pan 6/16/2021 Not Ready for Inspection KRISTEN CAUSEY
Shower Pan 6/22/2021 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 11/2/2023 Approved DAVID SCANTLIN
Final 11/2/2023 Corrections Issued DAVID SCANTLIN
Interior/Exterior Lathing 11/2/2023 Approved DAVID SCANTLIN
MERV13>=Rough 11/2/2023 Approved DAVID SCANTLIN
PLUMBING-Rough 11/2/2023 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 11/2/2023 Approved DAVID SCANTLIN
Final 12/13/2023 Corrections Issued DAVID SCANTLIN
Green Building Final 12/13/2023 Approved DAVID SCANTLIN
MERV13>=Final 12/13/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 12/13/2023 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 12/13/2023 Approved DAVID SCANTLIN
Final 4/3/2024 OK to Issue CofO DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 4/3/2024 SGSOV Approved DAVID SCANTLIN