15647 W TULSA ST 91344
Certificate Information: 15647 W TULSA ST 91344
- Application / Permit
- 20010-20000-00576
- Plan Check / Job No.
- B20VN03136
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22'-6" x 41' ONE-STORY DETACHED ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 7/16/2020
- Issuing Office
- Current Status
- CofO Issued on 2/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | SEAN SHAHMIRI |
| Corrections Issued | 3/31/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 4/10/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 4/17/2020 | APPLICANT |
| Green Plans Picked Up | 4/17/2020 | APPLICANT |
| Plan Check Approved | 7/9/2020 | SEAN SHAHMIRI |
| Issued | 7/16/2020 | APPLICANT |
| CofO in Progress | 12/15/2020 | MARK JOHNSON |
| CofO Issued | 2/6/2021 | MICHAEL SMITH |
| Permit Finaled | 2/6/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/6/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/6/2020 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 4/20/2020 | RIDWAN HARDY |
| Green Code | Cleared | 5/5/2020 | AARON COSTA |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/24/2020 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 6/25/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 7/2/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/2/2020 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sarkisian,, Armen; Lic. No.: C79287 | 913 UNIVERSITY AVENUE BURBANK, CA 91504 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/21/2020 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 7/27/2020 | Approved | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2020 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 8/24/2020 | Approved | WILLIAM KUEHN |
| HVAC-Rough | 8/24/2020 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 8/24/2020 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 9/2/2020 | Approved | MARK JOHNSON |
| Drywall Nailing | 9/2/2020 | Approved | MARK JOHNSON |
| Green Building Rough | 9/2/2020 | Approved | MARK JOHNSON |
| MERV13>=Rough | 9/2/2020 | Approved | MARK JOHNSON |
| Verify Sprinkler Sign Off | 9/2/2020 | Approved | MARK JOHNSON |
| Sewer | 9/22/2020 | Approved | MARK JOHNSON |
| Shower Pan | 9/22/2020 | Approved | MARK JOHNSON |
| Underground Mechanical | 9/22/2020 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 10/6/2020 | Approved | MARK JOHNSON |
| Final | 11/5/2020 | Corrections Issued | WILLIAM KUEHN |
| Green Building Final | 11/5/2020 | Approved | WILLIAM KUEHN |
| MERV13>=Final | 11/5/2020 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 11/5/2020 | SGSOV Approved | WILLIAM KUEHN |
| Service/Power Release | 11/5/2020 | Approved | WILLIAM KUEHN |
| Smoke Detectors | 11/5/2020 | Approved | WILLIAM KUEHN |
| Final | 12/14/2020 | OK to Issue CofO | MARK JOHNSON |