10631 1/2 N COLLETT AVE 91344

Certificate Information: 10631 1/2 N COLLETT AVE 91344

Application / Permit
20010-20000-00574
Plan Check / Job No.
B20VN03129
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW TWO STORY ACCESSORY DWELLING UNIT ( 28'-2"X26'-0") fire sprinkler nfpa 13D
Permit Issued
Issued on 5/19/2023
Issuing Office
Current Status
CofO Issued on 4/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 MOHAMMAD ESMAILI
Green Plans Picked Up 3/19/2020 APPLICANT
Corrections Issued 3/25/2020 MOHAMMAD ESMAILI
Quality Review Completed 4/6/2020 OMID HEDAYAT
Building Plans Picked Up 4/8/2020 APPLICANT
Plan Check Approved 5/19/2023 MOHAMMAD ESMAILI
Issued 5/19/2023 APPLICANT
CofO in Progress 2/8/2024 JAVIER RAMOS JR
Permit Finaled 4/11/2024 RUBEN SALAS
CofO Issued 4/11/2024 RUBEN SALAS
Permit Finaled 4/11/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/17/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 4/24/2020 GUILLERMO PETRA
Sewer availability Cleared 4/24/2020 GUILLERMO PETRA
Low Impact Development Cleared 3/17/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 3/18/2023 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 3/18/2023 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 4/18/2023 GILBERT URREA
Green Code Cleared 5/19/2023 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Wassef,, Mena Maher Salama; Lic. No.: C84979 28131 VALERIO CT      VALENCIA, CA 91354

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/30/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/30/2023 Partial Approval JAVIER RAMOS JR
Gas Test 8/9/2023 Partial Approval JAVIER RAMOS JR
Sewer 8/9/2023 Approved JAVIER RAMOS JR
Underground Mechanical 8/9/2023 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 8/10/2023 Partial Inspection JAVIER RAMOS JR
Deputy Drilled-In Anchors 8/10/2023 Conditional Approval JAVIER RAMOS JR
Deputy Wood Construction 8/10/2023 Conditional Approval JAVIER RAMOS JR
ELECTRICAL-Rough 8/10/2023 Approved JAVIER RAMOS JR
Green Building Rough 8/10/2023 Approved JAVIER RAMOS JR
HVAC-Rough 8/10/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 8/10/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/8/2023 Corrections Issued JAVIER RAMOS JR
Shower Pan 9/8/2023 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 9/8/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 9/22/2023 Approved JAVIER RAMOS JR
Insulation 9/22/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/22/2023 Approved JAVIER RAMOS JR
Drywall Nailing 9/27/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 1/8/2024 Approved JAVIER RAMOS JR
Final 1/8/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 1/8/2024 Approved JAVIER RAMOS JR
Green Building Final 1/8/2024 Approved JAVIER RAMOS JR
HVAC-Final 1/8/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 1/8/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/8/2024 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 1/8/2024 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 1/8/2024 Approved JAVIER RAMOS JR
Final 1/18/2024 Partial Inspection JAVIER RAMOS JR
Final 2/7/2024 No Access for Inspection CRAIG DAVIS
Final 2/8/2024 OK to Issue CofO JAVIER RAMOS JR