7950 N WHITE OAK AVE 91325

Certificate Information: 7950 N WHITE OAK AVE 91325

Application / Permit
20010-20000-00555
Plan Check / Job No.
B20VN02968
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 39' X 40' ONE STORY DETACHED ACCESSORY DWELLING UNIT WITH 4' X 10' COVERED ENTRY PORCH ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/28/2020
Issuing Office
Current Status
CofO Issued on 12/8/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 3/27/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 4/6/2020 OMID HEDAYAT
Building Plans Picked Up 4/6/2020 APPLICANT
Green Plans Picked Up 4/27/2020 APPLICANT
Plan Check Approved 5/28/2020 SEWADA ZADOORAN MILAGARDI
Issued 5/28/2020 APPLICANT
CofO in Progress 11/13/2020 DANIEL ORRANTE
CofO Issued 12/8/2020 MICHAEL SMITH
Permit Finaled 12/8/2020 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 4/28/2020 ANDRES COVARRUBIAS
Green Code Cleared 5/1/2020 AARON COSTA
Address approval Cleared 5/11/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/12/2020 GABRIEL ROBLES
Sewer availability Cleared 5/12/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 5/13/2020 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 5/15/2020 ADRIAN CASTRO

Contact Information

Architect Gemigniani,, Richard Louis; Lic. No.: C18783 14263 VALLEY VISTA BLVD.      SHERMAN OAKS, CA 91403
Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/10/2020 Approved JEFFREY PARD
Underground Mechanical 6/10/2020 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/19/2020 Approved MATTHEW NELSON
PLUMBING-Rough 6/19/2020 Partial Inspection MATTHEW NELSON
Insulation 6/22/2020 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/24/2020 Approved DANIEL DREW
ELECTRICAL-Rough 7/16/2020 Not Ready for Inspection PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 7/16/2020 Not Ready for Inspection PIERRE VEGA
HVAC-Rough 7/16/2020 Not Ready for Inspection PIERRE VEGA
PLUMBING-Rough 7/16/2020 Corrections Issued PIERRE VEGA
BUILDING-Rough-Frame 7/20/2020 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 7/20/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 7/20/2020 Not Ready for Inspection JOHN HAYES
HVAC-Rough 7/20/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 7/20/2020 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 7/20/2020 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 7/23/2020 Corrections Issued MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 7/23/2020 Corrections Issued MICHAEL TEMPLE
HVAC-Rough 7/23/2020 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 7/23/2020 Not Ready for Inspection MICHAEL TEMPLE
Underground Mechanical 7/23/2020 Not Ready for Inspection MICHAEL TEMPLE
BUILDING-Rough-Frame 7/28/2020 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Rough 7/28/2020 Corrections Issued DANIEL DREW
Green Building Rough 7/28/2020 Not Ready for Inspection DANIEL DREW
HVAC-Rough 7/28/2020 Approved DANIEL DREW
PLUMBING-Rough 7/28/2020 Corrections Issued DANIEL DREW
Verify Sprinkler Sign Off 7/28/2020 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Rough 7/30/2020 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 7/30/2020 Approved DANIEL DREW
HVAC-Rough 7/30/2020 Approved DANIEL DREW
PLUMBING-Rough 7/30/2020 Approved DANIEL DREW
Insulation 8/4/2020 Not Ready for Inspection DONALD SUNSERI
Interior/Exterior Lathing 8/4/2020 Not Ready for Inspection DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 8/7/2020 Not Ready for Inspection WILLIAM KUEHN
Insulation 8/7/2020 Approved WILLIAM KUEHN
Interior/Exterior Lathing 8/7/2020 Partial Inspection WILLIAM KUEHN
Drywall Nailing 8/11/2020 Approved MICHAEL TEMPLE
Green Building Rough 8/11/2020 Approved MICHAEL TEMPLE
Interior/Exterior Lathing 8/27/2020 Approved DONALD SUNSERI
BUILDING-Rough-Frame 11/2/2020 Approved JENNIFER RABUCHIN
Final 11/2/2020 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 11/2/2020 Approved JENNIFER RABUCHIN
Green Building Final 11/2/2020 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/2/2020 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 11/2/2020 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 11/2/2020 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 11/2/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/9/2020 Approved DANIEL ORRANTE
Final 11/9/2020 OK to Issue CofO DANIEL ORRANTE
Green Building Final 11/9/2020 Approved DANIEL ORRANTE
SGSOV-Seismic Gas S/O Valve 11/9/2020 SGSOV Approved DANIEL ORRANTE
Service/Power Release 11/9/2020 Approved DANIEL ORRANTE