5041 N NOELINE AVE 91436
Certificate Information: 5041 N NOELINE AVE 91436
- Application / Permit
- 20010-20000-00552
- Plan Check / Job No.
- B20VN02958
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 82'-6" X 54' (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/5/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | SELLA BENYAMIN |
| Corrections Issued | 3/17/2020 | SELLA BENYAMIN |
| Quality Review Completed | 3/18/2020 | STEVEN KIM |
| Building Plans Picked Up | 3/31/2020 | APPLICANT |
| Green Plans Picked Up | 3/31/2020 | APPLICANT |
| Plan Check Approved | 6/4/2020 | SELLA BENYAMIN |
| Issued | 6/5/2020 | LADBS |
| CofO in Progress | 4/8/2021 | RONALD COWAN |
| Permit Finaled | 4/26/2021 | MICHAEL SMITH |
| CofO Issued | 4/26/2021 | MICHAEL SMITH |
| Permit Finaled | 4/26/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 3/19/2020 | JOHN KIM |
| Public Works-Highway Ded. | Cleared | 4/2/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2020 | LEE GUILBEAUX |
| Permit | Cleared | 4/21/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/21/2020 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 5/8/2020 | KURT CORRAL |
| Green Code | Cleared | 5/12/2020 | MICHAEL AYERS |
| Low Impact Development | Cleared | 5/21/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 5/21/2020 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/11/2020 | Not Ready for Inspection | RONALD COWAN |
| Footing/Foundation/Slab | 6/11/2020 | Not Ready for Inspection | RONALD COWAN |
| Underground Mechanical | 6/11/2020 | Not Ready for Inspection | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 6/15/2020 | Approved | RONALD COWAN |
| Structural Steel Frame | 6/15/2020 | Partial Approval | RONALD COWAN |
| Underground Mechanical | 6/15/2020 | Approved | RONALD COWAN |
| Deputy Steel/Welding | 6/16/2020 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 6/17/2020 | Approved | RONALD COWAN |
| Structural Steel Frame | 6/17/2020 | Partial Approval | RONALD COWAN |
| Deputy Steel/Welding | 6/19/2020 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2020 | Not Ready for Inspection | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2020 | Not Ready for Inspection | DONALD SUNSERI |
| ELECTRICAL-Rough | 8/3/2020 | No Access for Inspection | RONALD COWAN |
| HVAC-Rough | 8/3/2020 | No Access for Inspection | RONALD COWAN |
| PLUMBING-Rough | 8/3/2020 | Not Ready for Inspection | RONALD COWAN |
| Shower Pan | 8/3/2020 | No Access for Inspection | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2020 | No Access for Inspection | RONALD COWAN |
| Wood Frame | 8/11/2020 | No Access for Inspection | RONALD COWAN |
| ELECTRICAL-Rough | 8/12/2020 | Not Ready for Inspection | RONALD COWAN |
| Gas Test | 8/12/2020 | Not Ready for Inspection | RONALD COWAN |
| HVAC-Rough | 8/12/2020 | Not Ready for Inspection | RONALD COWAN |
| PLUMBING-Rough | 8/12/2020 | Not Ready for Inspection | RONALD COWAN |
| Shower Pan | 8/12/2020 | Not Ready for Inspection | RONALD COWAN |
| Wood Frame | 8/12/2020 | Not Ready for Inspection | RONALD COWAN |
| ELECTRICAL-Rough | 8/13/2020 | Not Ready for Inspection | RONALD COWAN |
| HVAC-Rough | 8/13/2020 | Not Ready for Inspection | RONALD COWAN |
| Insulation | 8/13/2020 | Not Ready for Inspection | RONALD COWAN |
| PLUMBING-Rough | 8/13/2020 | Not Ready for Inspection | RONALD COWAN |
| Interior/Exterior Lathing | 8/17/2020 | Partial Approval | RONALD COWAN |
| PLUMBING-Rough | 8/17/2020 | Approved | RONALD COWAN |
| Insulation | 8/24/2020 | Approved | RONALD COWAN |
| Drywall Nailing | 8/25/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 8/25/2020 | Approved | RONALD COWAN |
| ELECTRICAL-Final | 12/3/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Final | 12/3/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Final | 12/9/2020 | Approved | RONALD COWAN |
| HVAC-Final | 12/9/2020 | Approved | RONALD COWAN |
| PLUMBING-Final | 12/9/2020 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 1/22/2021 | Approved | RONALD COWAN |
| Final | 1/22/2021 | Not Ready for Inspection | RONALD COWAN |
| Gas Test | 1/22/2021 | Approved | RONALD COWAN |
| Green Building Final | 1/22/2021 | Approved | RONALD COWAN |
| Green Building Rough | 1/22/2021 | Approved | RONALD COWAN |
| MERV13>=Final | 1/22/2021 | Approved | RONALD COWAN |
| MERV13>=Rough | 1/22/2021 | Approved | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 1/22/2021 | SGSOV Approved | RONALD COWAN |
| Service/Power Release | 1/22/2021 | Approved | RONALD COWAN |
| Smoke Detectors | 1/22/2021 | Approved | RONALD COWAN |
| Verify Sprinkler Sign Off | 1/22/2021 | Approved | RONALD COWAN |
| Final | 1/27/2021 | Not Ready for Inspection | RONALD COWAN |
| Service/Power Release | 1/27/2021 | Approved | RONALD COWAN |
| Verify Rec and Parks Fee Memo | 1/27/2021 | Approved | RONALD COWAN |
| Final | 2/12/2021 | Corrections Issued | RONALD COWAN |
| Final | 2/18/2021 | Corrections Issued | RONALD COWAN |
| Final | 2/23/2021 | Corrections Issued | RONALD COWAN |
| Final | 3/2/2021 | Corrections Issued | RONALD COWAN |
| Final | 3/9/2021 | Corrections Issued | RONALD COWAN |
| Final | 4/7/2021 | OK to Issue CofO | RONALD COWAN |