9596 N BEACHY AVE 91331

Certificate Information: 9596 N BEACHY AVE 91331

Application / Permit
20010-20000-00541
Plan Check / Job No.
B20VN02895
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20' x 24'-9" ONE-STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g). ALL WORK PER WFPP.
Permit Issued
Issued on 2/19/2021
Issuing Office
Valley
Current Status
CofO Issued on 9/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2020 APPLICANT
Green Plans Picked Up 3/3/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 SEAN SHAHMIRI
Corrections Issued 3/16/2020 SEAN SHAHMIRI
Quality Review Completed 3/17/2020 OMID HEDAYAT
Building Plans Picked Up 3/17/2020 APPLICANT
Applicant returned to address corrections 11/30/2020 SEAN SHAHMIRI
Applicant returned to address corrections 1/4/2021 SEAN SHAHMIRI
Applicant returned to address corrections 1/22/2021 SEAN SHAHMIRI
Plan Check Approved 2/19/2021 SEAN SHAHMIRI
Issued 2/19/2021 APPLICANT
Applicant returned to address corrections 2/22/2021 SEAN SHAHMIRI
CofO in Progress 6/15/2021 GREGG CUMMINGS
Permit Finaled 9/9/2021 MICHAEL SMITH
CofO Issued 9/9/2021 MICHAEL SMITH
Permit Finaled 9/9/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/15/2020 GABRIEL ROBLES
Sewer availability Cleared 6/15/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/2/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 12/8/2020 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 2/16/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Ultimate Green Construction Inc; Lic. No.: 1023605-B 13302 FILMORE ST      PACOIMA, CA 91331

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/2/2021 Partial Approval BEAU COLLINS
PLUMBING-Rough 3/2/2021 Partial Approval BEAU COLLINS
Excavation/Setback/Form/Re-Bar 3/8/2021 Approved GREGG CUMMINGS
Footing/Foundation/Slab 3/8/2021 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 4/6/2021 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 4/6/2021 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 4/6/2021 Approved GREGG CUMMINGS
HVAC-Rough 4/6/2021 Approved GREGG CUMMINGS
PLUMBING-Rough 4/6/2021 Approved GREGG CUMMINGS
Insulation 4/14/2021 Approved DANIEL ORRANTE
Interior/Exterior Lathing 4/14/2021 Approved DANIEL ORRANTE
Underground Mechanical 4/14/2021 Approved DANIEL ORRANTE
Drywall Nailing 4/22/2021 Approved GREGG CUMMINGS
Green Building Rough 4/22/2021 Approved GREGG CUMMINGS
Sewer 4/22/2021 Approved GREGG CUMMINGS
Underground Mechanical 4/22/2021 Approved GREGG CUMMINGS
Special/Order Compliance 4/28/2021 Partial Inspection DANIEL ORRANTE
BUILDING-Rough-Frame 6/15/2021 Approved GREGG CUMMINGS
ELECTRICAL-Final 6/15/2021 Approved GREGG CUMMINGS
Final 6/15/2021 OK to Issue CofO GREGG CUMMINGS
Green Building Final 6/15/2021 Approved GREGG CUMMINGS
HVAC-Final 6/15/2021 Approved GREGG CUMMINGS
PLUMBING-Final 6/15/2021 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 6/15/2021 SGSOV Approved GREGG CUMMINGS
Service/Power Release 6/15/2021 Approved GREGG CUMMINGS
Smoke Detectors 6/15/2021 Approved GREGG CUMMINGS
Verify Sprinkler Sign Off 6/15/2021 Approved GREGG CUMMINGS