12758 N HADDON AVE 91342

Certificate Information: 12758 N HADDON AVE 91342

Application / Permit
20010-20000-00528
Plan Check / Job No.
B20VN02814
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE L-SHAPED 24'-10"X24'-9" DETACHED ONE STORY ACCESSORY DWELLING UNIT
Permit Issued
Issued on 5/22/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 DAWN MC NULTY
Corrections Issued 3/16/2020 DAWN MC NULTY
Quality Review Completed 3/16/2020 CHON CHIO KUO
Building Plans Picked Up 3/17/2020 APPLICANT
Green Plans Picked Up 3/17/2020 APPLICANT
Plan Check Approved 5/7/2020 DAWN MC NULTY
Issued 5/22/2020 LADBS
CofO in Progress 12/22/2020 MISAEL ESPARZA
CofO Issued 2/13/2021 MICHAEL SMITH
Permit Finaled 2/13/2021 MICHAEL SMITH

Permit Application Clearance Information

CPC Cleared 4/3/2020 MIGUEL GAMBOA
Address approval Cleared 4/6/2020 ADRIAN CASTRO
Permit Cleared 4/6/2020 ADRIAN CASTRO
Green Code Cleared 4/7/2020 MICHAEL AYERS
Hydrant and Access approval Cleared 4/20/2020 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 4/29/2020 PAMELA TENEZA
Sewer availability Cleared 4/29/2020 PAMELA TENEZA
Grading Pre-Inspection Cleared 5/7/2020 DAWN MC NULTY
Roof/Waste drainage to street Cleared 5/8/2020 ADRIAN CASTRO

Contact Information

Contractor Metro Builders And Remodeling Inc; Lic. No.: 768748-B 6520 PLATT AVENUE #430      WEST HILLS, CA 91307
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/27/2020 Approved TROY SANDERS
PLUMBING-Rough 5/27/2020 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 6/19/2020 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 6/19/2020 Corrections Issued GREGG CUMMINGS
Green Building Rough 6/19/2020 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 6/19/2020 Not Ready for Inspection GREGG CUMMINGS
Verify Sprinkler Sign Off 6/19/2020 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 6/24/2020 Approved GREGG CUMMINGS
ELECTRICAL-Rough 6/24/2020 Approved GREGG CUMMINGS
Green Building Rough 6/24/2020 Approved GREGG CUMMINGS
PLUMBING-Rough 6/24/2020 Approved GREGG CUMMINGS
Special/Order Compliance 6/24/2020 Partial Inspection PIERRE VEGA
Verify Sprinkler Sign Off 6/24/2020 Approved GREGG CUMMINGS
HVAC-Rough 6/26/2020 Approved GREGG CUMMINGS
Insulation 6/26/2020 Corrections Issued GREGG CUMMINGS
Insulation 6/30/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 6/30/2020 Approved GREGG CUMMINGS
Underground Mechanical 6/30/2020 Partial Approval GREGG CUMMINGS
Drywall Nailing 7/2/2020 Approved GREGG CUMMINGS
Sewer 7/15/2020 Corrections Issued GREGG CUMMINGS
Sewer 7/17/2020 Partial Approval GREGG CUMMINGS
Sewer 7/22/2020 Approved MISAEL ESPARZA
Final 8/11/2020 Corrections Issued MISAEL ESPARZA
Green Building Final 8/11/2020 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/11/2020 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 8/11/2020 Corrections Issued MISAEL ESPARZA
Smoke Detectors 8/11/2020 Not Ready for Inspection MISAEL ESPARZA
Final 8/24/2020 Corrections Issued MISAEL ESPARZA
Green Building Final 8/24/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/24/2020 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 8/24/2020 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 8/24/2020 Corrections Issued MISAEL ESPARZA
Final 8/26/2020 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/26/2020 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 8/26/2020 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 8/26/2020 Approved MISAEL ESPARZA
Final 9/8/2020 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/8/2020 SGSOV Approved MISAEL ESPARZA
Service/Power Release 9/8/2020 Not Ready for Inspection MISAEL ESPARZA
Final 9/17/2020 Not Ready for Inspection MISAEL ESPARZA
Service/Power Release 9/17/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 12/21/2020 Approved MISAEL ESPARZA
Final 12/21/2020 OK to Issue CofO MISAEL ESPARZA
HVAC-Final 12/21/2020 Approved MISAEL ESPARZA
PLUMBING-Final 12/21/2020 Approved MISAEL ESPARZA
Service/Power Release 12/21/2020 Approved MISAEL ESPARZA
Special/Order Compliance 1/11/2021 Approved MISAEL ESPARZA