2617 S CLYDE AVE 90016

Certificate Information: 2617 S CLYDE AVE 90016

Application / Permit
20010-20000-00527
Plan Check / Job No.
B20VN02806
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRREGULAR 32'-0" X 37'-9" DETACHED ACCESSORY DWELLING UNIT W/ 19'-0" X 19'-1" ATTACHED 2-CAR GARAGE AND 9'-5" X 30'-3" ROOF DECK PER GCS 65852.2(E)(1)(B). ALL WORK PER ENGINEERING. [NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT]
Permit Issued
Issued on 3/10/2021
Issuing Office
Current Status
CofO Issued on 9/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2020 APPLICANT
Green Plans Picked Up 3/5/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 JENNIFER LEE
Corrections Issued 3/20/2020 JENNIFER LEE
Quality Review Completed 3/20/2020 STEVEN KIM
Applicant returned to address corrections 1/6/2021 JENNIFER LEE
Applicant returned to address corrections 2/17/2021 JENNIFER LEE
Plan Check Approved 3/9/2021 JENNIFER LEE
Issued 3/10/2021 APPLICANT
Building Plans Picked Up 9/9/2021 APPLICANT
CofO in Progress 8/22/2022 JOSE AVILA
Permit Finaled 9/16/2022 DEROLD HAUFF
CofO Issued 9/16/2022 DEROLD HAUFF
Permit Finaled 9/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/31/2020 JEANIE LAM
Green Code Cleared 9/9/2020 AARON COSTA
Sewer availability Cleared 9/14/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/25/2020 PAMELA TENEZA
Low Impact Development Cleared 11/30/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 12/1/2020 JEANIE LAM
Hydrant and Access approval Cleared 1/22/2021 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/23/2021 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 5/4/2021 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 5/4/2021 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 5/6/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 5/6/2021 Approved STUART CHAPMAN
PLUMBING-Rough 5/13/2021 Off-Hour Fees Due
PLUMBING-Rough 5/19/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/28/2021 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 7/6/2021 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 8/3/2021 Corrections Issued SCOTT FINNILA
HVAC-Rough 8/3/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 8/3/2021 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 8/10/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 8/10/2021 Approved KATHRYN BUTTERWORTH
Underground Mechanical 8/10/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 8/31/2021 Partial Approval ALAN MORELOS
HVAC-Rough 10/5/2021 Corrections Issued SCOTT FINNILA
Wood Frame 10/5/2021 Partial Approval SCOTT FINNILA
Special/Order Compliance 10/18/2021 Partial Inspection LILIANA PORTILLO
Wood Frame 10/18/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 10/27/2021 Approved JOSE AVILA
Wood Frame 10/27/2021 Approved JOSE AVILA
Insulation 11/2/2021 Corrections Issued JOSE AVILA
Insulation 11/4/2021 Approved JOSE AVILA
Drywall Nailing 11/12/2021 Partial Approval JUSTIN HAWLEY
Green Building Rough 11/12/2021 Approved JUSTIN HAWLEY
Shower Pan 11/12/2021 Not Ready for Inspection JUSTIN HAWLEY
Drywall Nailing 11/17/2021 Approved ADAM ESCOTO
Shower Pan 11/17/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 12/2/2021 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 1/24/2022 Approved JOSE AVILA
ELECTRICAL-Final 5/16/2022 Corrections Issued JOSE AVILA
Service/Power Release 5/16/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Final 5/19/2022 Approved JOSE AVILA
Service/Power Release 5/19/2022 Approved JOSE AVILA
Gas Test 6/24/2022 Approved JOSE AVILA
Pre-Inspection 6/24/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 7/7/2022 Conditional Approval JOSE AVILA
Final 7/7/2022 Corrections Issued JOSE AVILA
Green Building Final 7/7/2022 Partial Approval JOSE AVILA
HVAC-Final 7/7/2022 Corrections Issued JOSE AVILA
MERV13>=Final 7/7/2022 Approved JOSE AVILA
MERV13>=Rough 7/7/2022 Approved JOSE AVILA
PLUMBING-Final 7/7/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/7/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 7/7/2022 Approved JOSE AVILA
Verify Sprinkler Sign Off 7/7/2022 Corrections Issued JOSE AVILA
HVAC-Final 7/14/2022 Approved JOSE AVILA
PLUMBING-Final 7/14/2022 Partial Inspection JOSE AVILA
BUILDING-Rough-Frame 7/21/2022 Approved JOSE AVILA
Final 7/21/2022 Corrections Issued JOSE AVILA
Green Building Final 7/21/2022 Approved JOSE AVILA
Verify Sprinkler Sign Off 7/21/2022 Approved JOSE AVILA
Final 8/19/2022 OK to Issue CofO JOSE AVILA