11844 W OTSEGO ST 91607
Certificate Information: 11844 W OTSEGO ST 91607
- Application / Permit
- 20010-20000-00510
- Plan Check / Job No.
- B20VN02753
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE IRREG. 46'X65' TWO STORY SFD WITH ATTACHED GARAGE, TRELLIS AT REAR, AND COVERED ENTRY _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D. *affidavit for linkage fee 3 years not to sell
- Permit Issued
- Issued on 8/12/2020
- Issuing Office
- Current Status
- CofO Issued on 5/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | DAWN MC NULTY |
| Corrections Issued | 3/16/2020 | DAWN MC NULTY |
| Quality Review Completed | 3/18/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/20/2020 | APPLICANT |
| Green Plans Picked Up | 3/20/2020 | APPLICANT |
| Plan Check Approved | 8/12/2020 | DAWN MC NULTY |
| Issued | 8/12/2020 | APPLICANT |
| CofO in Progress | 3/23/2021 | THOMAS FINNILA |
| Permit Finaled | 5/8/2021 | MICHAEL SMITH |
| CofO Issued | 5/8/2021 | MICHAEL SMITH |
| Permit Finaled | 5/8/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/27/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2020 | GABRIEL ROBLES |
| Permit | Cleared | 4/27/2020 | GABRIEL ROBLES |
| Frnt yard landscape/Water mgmt | Cleared | 5/11/2020 | OLGA AYALA |
| Specific Plan | Cleared | 5/11/2020 | OLGA AYALA |
| Low Impact Development | Cleared | 6/12/2020 | DAWN MC NULTY |
| CPC | Cleared | 6/23/2020 | MIGUEL GAMBOA |
| Roof/Waste drainage to street | Cleared | 7/2/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 7/14/2020 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 7/15/2020 | MATTHEW CRAIG |
| Sewer availability | Cleared | 7/15/2020 | GABRIEL ROBLES |
| Trees in Parkway | Cleared | 7/21/2020 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/25/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Underground Mechanical | 8/25/2020 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/1/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Reinf. Concrete | 9/2/2020 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/3/2020 | Approved | THOMAS FINNILA |
| Deputy Reinf. Concrete | 9/4/2020 | Conditional Approval | THOMAS FINNILA |
| Wood Frame | 9/9/2020 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 9/11/2020 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Rough | 10/1/2020 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/14/2020 | Approved | THOMAS FINNILA |
| HVAC-Rough | 10/14/2020 | Partial Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Conditional Approval | THOMAS FINNILA |
| HVAC-Rough | 10/23/2020 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2020 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 10/26/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/30/2020 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 10/30/2020 | Approved | THOMAS FINNILA |
| Wood Frame | 10/30/2020 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/5/2020 | Approved | THOMAS FINNILA |
| Green Building Rough | 11/5/2020 | Approved | THOMAS FINNILA |
| Insulation | 11/5/2020 | Approved | THOMAS FINNILA |
| Shower Pan | 11/5/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 11/5/2020 | Approved | THOMAS FINNILA |
| Drywall Nailing | 11/13/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/13/2020 | Approved | THOMAS FINNILA |
| Shower Pan | 11/13/2020 | Approved | THOMAS FINNILA |
| Enclosure/Fence | 2/8/2021 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 2/12/2021 | Approved | THOMAS FINNILA |
| HVAC-Final | 2/17/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 2/22/2021 | Approved | THOMAS FINNILA |
| Final | 3/3/2021 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 3/3/2021 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/3/2021 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 3/3/2021 | Corrections Issued | THOMAS FINNILA |
| Smoke Detectors | 3/3/2021 | Approved | THOMAS FINNILA |
| Final | 3/9/2021 | Not Ready for Inspection | BEAU COLLINS |
| Service/Power Release | 3/9/2021 | Not Ready for Inspection | BEAU COLLINS |
| Final | 3/23/2021 | OK to Issue CofO | THOMAS FINNILA |
| Service/Power Release | 3/23/2021 | Approved | THOMAS FINNILA |
| Service/Power Release | 3/24/2021 | Approved | THOMAS FINNILA |