- Work Description
- NEW 27'-8" X 23' (3) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/8/2020
- Issuing Office
- Current Status
- CofO Issued on 11/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | SELLA BENYAMIN |
| Green Plans Picked Up | 3/19/2020 | APPLICANT |
| Corrections Issued | 4/3/2020 | SELLA BENYAMIN |
| Quality Review Completed | 4/3/2020 | STEVEN KIM |
| Building Plans Picked Up | 4/6/2020 | APPLICANT |
| Plan Check Approved | 10/7/2020 | SELLA BENYAMIN |
| Issued | 10/8/2020 | APPLICANT |
| CofO in Progress | 11/1/2022 | RONALD MYRICK |
| Permit Finaled | 11/1/2022 | RONALD MYRICK |
| CofO Issued | 11/1/2022 | RONALD MYRICK |
| Permit Finaled | 11/1/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/27/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 8/3/2020 | ANDRES COVARRUBIAS |
| Address approval | Cleared | 8/12/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2020 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 8/13/2020 | ELAINE LEI |
| Sewer availability | Cleared | 8/13/2020 | ELAINE LEI |
| Green Code | Cleared | 8/18/2020 | MICHAEL AYERS |
| GPI Written Notices | Cleared | 9/23/2020 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 9/23/2020 | SELLA BENYAMIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/23/2020 | Partial Inspection | ROBERT VORHIS |
| PLUMBING-Rough | 12/29/2020 | Partial Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 1/12/2021 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2021 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2021 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 5/10/2021 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Rough | 5/10/2021 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 5/10/2021 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Rough | 5/13/2021 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 5/13/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 5/24/2021 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 6/3/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Green Building Rough | 6/3/2021 | Not Ready for Inspection | ROBERT VORHIS |
| MERV13>=Rough | 6/3/2021 | Approved | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 6/3/2021 | Not Ready for Inspection | ROBERT VORHIS |
| BUILDING-Rough-Frame | 6/17/2021 | Approved | ROBERT VORHIS |
| Green Building Rough | 6/17/2021 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 6/17/2021 | Approved | ROBERT VORHIS |
| Shower Pan | 6/17/2021 | Approved | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 6/17/2021 | Approved | ROBERT VORHIS |
| Wood Frame | 6/17/2021 | Approved | ROBERT VORHIS |
| Insulation | 6/29/2021 | Approved | WILLIAM WREN |
| Drywall Nailing | 7/27/2021 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 8/25/2021 | Approved | ROBERT VORHIS |
| Underground Mechanical | 8/31/2021 | Partial Approval | HORACE FULTZ |
| Sewer | 11/8/2021 | Approved | JUSTIN HAWLEY |
| Final | 8/11/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 8/11/2022 | Partial Inspection | FREDDIE RIVERA |
| MERV13>=Final | 8/11/2022 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/11/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 8/11/2022 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 8/11/2022 | Partial Inspection | FREDDIE RIVERA |
| Final | 8/19/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 8/19/2022 | Corrections Issued | FREDDIE RIVERA |
| MERV13>=Final | 8/19/2022 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/19/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 8/19/2022 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 8/19/2022 | Partial Inspection | FREDDIE RIVERA |
| Final | 9/6/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 9/6/2022 | Conditional Approval | FREDDIE RIVERA |
| MERV13>=Final | 9/6/2022 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 9/6/2022 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 9/6/2022 | Approved | FREDDIE RIVERA |
| Final | 9/21/2022 | Conditional Approval | FREDDIE RIVERA |
| Green Building Final | 9/21/2022 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 9/21/2022 | Approved | FREDDIE RIVERA |
| Service/Power Release | 9/21/2022 | Approved | FREDDIE RIVERA |