7611 N OAK PARK AVE 91406

Certificate Information: 7611 N OAK PARK AVE 91406

Application / Permit
20010-20000-00463
Plan Check / Job No.
B20VN02428
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ACCESSORY DWELLING UNIT ( 32'-1"x23'-9")
Permit Issued
Issued on 9/11/2020
Issuing Office
Current Status
CofO Issued on 6/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2020 APPLICANT
Green Plans Picked Up 3/11/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 MOHAMMAD ESMAILI
Corrections Issued 3/20/2020 MOHAMMAD ESMAILI
Quality Review Completed 4/6/2020 OMID HEDAYAT
Building Plans Picked Up 4/8/2020 APPLICANT
Applicant returned to address corrections 6/3/2020 MOHAMMAD ESMAILI
Plan Check Approved 9/2/2020 MOHAMMAD ESMAILI
Issued 9/11/2020 APPLICANT
CofO in Progress 5/24/2021 JENNIFER RABUCHIN
Permit Finaled 6/1/2021 MICHAEL SMITH
CofO Issued 6/1/2021 MICHAEL SMITH
Permit Finaled 6/1/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/6/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/12/2020 ADRIAN CASTRO
Sewer availability Cleared 6/12/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 7/6/2020 MATTHEW CRAIG
Green Code Cleared 7/7/2020 AARON COSTA
Green Code Cleared 7/7/2020 MOHAMMAD ESMAILI
Low Impact Development Cleared 8/9/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/13/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/28/2020 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 9/28/2020 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 10/2/2020 Approved MICHAEL TEMPLE
Underground Mechanical 10/2/2020 Partial Approval MICHAEL TEMPLE
ELECTRICAL-Rough 11/4/2020 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 11/4/2020 Not Ready for Inspection ARTHUR SARGSYAN
Wood Frame 11/4/2020 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Rough 12/4/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 12/4/2020 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 12/4/2020 Partial Approval ARTHUR SARGSYAN
HVAC-Rough 12/10/2020 Approved ARTHUR SARGSYAN
Wood Frame 12/10/2020 Approved ARTHUR SARGSYAN
Insulation 12/21/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 12/21/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 1/8/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 3/11/2021 Approved ARTHUR SARGSYAN
Final 3/11/2021 Corrections Issued ARTHUR SARGSYAN
Green Building Final 3/11/2021 Approved ARTHUR SARGSYAN
Green Building Rough 3/11/2021 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/11/2021 SGSOV Approved ARTHUR SARGSYAN
Service/Power Release 3/11/2021 Not Ready for Inspection ARTHUR SARGSYAN
Smoke Detectors 3/11/2021 Approved ARTHUR SARGSYAN
Verify Sprinkler Sign Off 3/11/2021 Approved ARTHUR SARGSYAN
Final 4/21/2021 Not Ready for Inspection ARTHUR SARGSYAN
Service/Power Release 4/21/2021 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Final 5/20/2021 Approved JENNIFER RABUCHIN
Final 5/20/2021 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 5/20/2021 Approved JENNIFER RABUCHIN
HVAC-Final 5/20/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/20/2021 Approved JENNIFER RABUCHIN
Service/Power Release 5/20/2021 Approved JENNIFER RABUCHIN