15724 W DEVONSHIRE ST #1-#11 91344

Certificate Information: 15724 W DEVONSHIRE ST #1-#11 91344

Application / Permit
20010-20000-00458
Plan Check / Job No.
B20VN02405
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3-STORY 11-UNITS APT /OVER ON GRADE PARKING GARAGE, TOTAL 4-STORY BUILDING - 1 OF 2
Permit Issued
Issued on 9/11/2020
Issuing Office
Current Status
Issued on 9/11/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/12/2020 APPLICANT
Disabled Access Plans Picked Up 2/26/2020 APPLICANT
Green Plans Picked Up 2/26/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 CHON CHIO KUO
Corrections Issued 3/2/2020 CHON CHIO KUO
Quality Review Completed 3/4/2020 GUANG MIN TUNG
Building Plans Picked Up 3/4/2020 APPLICANT
Applicant returned to address corrections 4/9/2020 CHON CHIO KUO
Applicant returned to address corrections 6/8/2020 CHON CHIO KUO
Applicant returned to address corrections 6/11/2020 CHON CHIO KUO
Applicant returned to address corrections 6/16/2020 CHON CHIO KUO
Applicant returned to address corrections 8/12/2020 CHON CHIO KUO
Plan Check Approved 8/13/2020 CHON CHIO KUO
Issued 9/11/2020 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/4/2020 ADRIAN CASTRO
Work Adjacent to Public Way Cleared 3/4/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/6/2020 JOHN LIN
Highway dedication Cleared 3/18/2020 GABRIEL ROBLES
Permit Cleared 3/18/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 4/7/2020 ROBERT DUFF
Trees in Parkway Cleared 4/8/2020 JOHN KIM
Building over 3-story or 36-ft Cleared 4/9/2020 CALOSHA APPROVED
Green Code Cleared 4/28/2020 MICHAEL AYERS
Sewer availability Cleared 4/28/2020 JOHN TRIANTAFYLLOS
Fire Marshall Fire Life Safety Cleared 5/6/2020 VIDAL GARCIA
Frnt yard landscape/Water mgmt Cleared 5/14/2020 PABLO ESTRADA
Opn space landscape/Water mgmt Cleared 5/14/2020 PABLO ESTRADA
Low Impact Development Cleared 5/25/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/27/2020 JOHN TRIANTAFYLLOS
DAS Clearance Cleared 7/28/2020 NORLITO MEDRANO

Contact Information

Contractor New Image Construction; Lic. No.: 843394-B 8928 CHIMINEAS AVE      NORTHRIDGE, CA 91325
Engineer Mesrop,, Mesrop Aram; Lic. No.: GE2561 7608 CLINTON ST      LOS ANGELES, CA 90036
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/22/2020 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 1/6/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 1/21/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 1/22/2021 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 2/11/2021 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 2/18/2021 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 3/31/2021 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 4/7/2021 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 4/21/2021 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 5/5/2021 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/12/2021 Partial Inspection DANNY RODRIGUEZ
Deputy Other (see comments) 5/14/2021 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/19/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/21/2021 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 6/14/2021 Partial Approval RICKEY JACKSON
Footing/Foundation/Slab 8/17/2021 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 12/1/2021 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 12/6/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 12/6/2021 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 12/6/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/6/2021 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/8/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 2/8/2022 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 2/8/2022 Partial Approval JOHN KITCKO
Green Building Rough 2/8/2022 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 3/11/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/11/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 3/11/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/11/2022 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 3/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Corrections Issued DANNY RODRIGUEZ
Green Building Rough 3/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 4/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 4/12/2022 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/21/2022 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/11/2022 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/30/2022 Partial Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 10/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 10/14/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 10/14/2022 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/14/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 10/27/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/27/2022 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 11/15/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 11/15/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/17/2022 Not Ready for Inspection JEFFREY FULTON
Wood Frame 11/17/2022 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 11/22/2022 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 11/22/2022 Not Ready for Inspection JEFFREY FULTON
Wood Frame 11/22/2022 Partial Inspection JEFFREY FULTON
Pre-Inspection 12/14/2022 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 12/14/2022 Partial Inspection DEANDRE HOFFMAN
Insulation 12/28/2022 Corrections Issued JEFFREY FULTON
Green Building Rough 1/9/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 1/9/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 1/9/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 2/1/2023 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 2/1/2023 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 2/1/2023 Partial Inspection DEANDRE HOFFMAN
Verify Sprinkler Sign Off 2/1/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 2/1/2023 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 4/10/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 4/10/2023 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 4/12/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 4/14/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 4/14/2023 Partial Inspection JEFFREY FULTON
Insulation 4/18/2023 Partial Inspection JEFFREY FULTON
Special/Order Compliance 4/18/2023 Conditional Approval STEVEN LEVITT
Wood Frame 4/18/2023 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 4/19/2023 Partial Inspection JEFFREY FULTON
Special/Order Compliance 4/19/2023 Conditional Approval STEVEN LEVITT
Insulation 4/20/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 4/20/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 4/24/2023 Approved JEFFREY FULTON
Insulation 4/24/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 4/24/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 5/18/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 5/18/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 5/24/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Wood Construction 5/25/2023 Conditional Approval JEFFREY FULTON
Insulation 8/10/2023 Partial Inspection JEFFREY FULTON
Wood Frame 8/14/2023 Partial Inspection JEFFREY FULTON
Insulation 8/25/2023 Partial Inspection JEFFREY FULTON
Insulation 11/20/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 11/29/2023 Partial Inspection JEFFREY FULTON
Wood Frame 11/29/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/5/2023 Partial Inspection JEFFREY FULTON
Insulation 12/5/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/6/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/6/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/6/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/11/2023 Partial Inspection JEFFREY FULTON
Insulation 12/11/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/11/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/11/2023 Partial Inspection JEFFREY FULTON
Insulation 12/14/2023 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 12/14/2023 Not Ready for Inspection JOHN KITCKO
Wood Frame 12/14/2023 Partial Approval JOHN KITCKO
Drywall Nailing 12/28/2023 Partial Inspection JEFFREY FULTON
Insulation 12/28/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/10/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 5/22/2024 Partial Inspection GREGORY POMISH
Wood Frame 5/22/2024 Partial Approval GREGORY POMISH
Insulation 5/24/2024 Partial Approval GREGORY POMISH
Drywall Nailing 5/29/2024 Partial Approval GREGORY POMISH
Pre-Inspection 7/23/2025 Partial Inspection GREGORY POMISH
Pre-Inspection 10/28/2025 Partial Inspection GREGORY POMISH
Masonry Wall/Backfill 2/23/2026 Partial Inspection GREGORY POMISH