13213 W OTSEGO ST 91423
Certificate Information: 13213 W OTSEGO ST 91423
- Application / Permit
- 20010-20000-00452
- Plan Check / Job No.
- B20VN02394
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (1 OF 2) NEW 64'2"X47'0" 2-STORY SFD WITH ATTACHED GARAGE. NFPA 13 D FIRE SPRINKLERS REQ'D THROUGHOUT
- Permit Issued
- Issued on 11/15/2020
- Issuing Office
- Current Status
- CofO Issued on 8/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | MARVEL DELACRUZ |
| Corrections Issued | 2/29/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 3/2/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 3/3/2020 | APPLICANT |
| Green Plans Picked Up | 3/3/2020 | APPLICANT |
| Applicant returned to address corrections | 4/3/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 5/26/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 6/30/2020 | MARVEL DELACRUZ |
| Issued | 11/15/2020 | APPLICANT |
| CofO in Progress | 8/18/2022 | RAFAEL CORTES |
| Permit Finaled | 8/19/2022 | MICHAEL SMITH |
| CofO Issued | 8/19/2022 | MICHAEL SMITH |
| Permit Finaled | 8/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/6/2020 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2020 | JOHN LIN |
| Permit | Cleared | 3/6/2020 | JOHN LIN |
| Sewer availability | Cleared | 3/6/2020 | JOHN LIN |
| Hydrant and Access approval | Cleared | 3/9/2020 | GEORGE SUCHAND |
| Construction near power lines | Cleared | 3/19/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/19/2020 | RIDWAN HARDY |
| Trees in Parkway | Cleared | 3/19/2020 | JOHN KIM |
| Green Code | Cleared | 4/8/2020 | MICHAEL AYERS |
| Low Impact Development | Cleared | 5/8/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 5/14/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/15/2021 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 7/15/2021 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Special/Order Compliance | 8/13/2021 | No Access for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 10/4/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/4/2021 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 10/4/2021 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 10/4/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/4/2021 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 10/4/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 10/29/2021 | Conditional Approval | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 10/29/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/8/2021 | Approved | ASHLEY THOMPSON |
| Shower Pan | 11/8/2021 | Approved | ASHLEY THOMPSON |
| Insulation | 11/16/2021 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 11/23/2021 | Conditional Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 2/28/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 2/28/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 5/2/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/11/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 7/11/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Final | 7/11/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 7/11/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 7/11/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Final | 7/11/2022 | Order to Comply Issued | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Not Ready | RAFAEL CORTES |
| Service/Power Release | 7/11/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Smoke Detectors | 7/11/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 7/11/2022 | Not Ready for Inspection | RAFAEL CORTES |
| BUILDING-Rough-Frame | 7/19/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 7/19/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Final | 7/19/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 7/19/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 7/19/2022 | Not Ready for Inspection | RAFAEL CORTES |
| HVAC-Final | 7/19/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Final | 7/19/2022 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 7/19/2022 | SGSOV Not Ready | RAFAEL CORTES |
| Service/Power Release | 7/19/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Smoke Detectors | 7/19/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 7/19/2022 | Not Ready for Inspection | RAFAEL CORTES |
| BUILDING-Rough-Frame | 8/2/2022 | Approved | RAFAEL CORTES |
| Drywall Nailing | 8/2/2022 | Approved | RAFAEL CORTES |
| Final | 8/2/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 8/2/2022 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 8/2/2022 | SGSOV Approved | RAFAEL CORTES |
| Service/Power Release | 8/2/2022 | Approved | RAFAEL CORTES |
| Smoke Detectors | 8/2/2022 | Approved | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 8/2/2022 | Approved | RAFAEL CORTES |
| HVAC-Final | 8/9/2022 | Corrections Issued | RAFAEL CORTES |
| Pre-Inspection | 8/9/2022 | Approved | RAFAEL CORTES |
| HVAC-Final | 8/15/2022 | No Access for Inspection | CALEB MEISTER |
| HVAC-Final | 8/16/2022 | Approved | RAFAEL CORTES |
| Service/Power Release | 8/16/2022 | Approved | RAFAEL CORTES |
| HVAC-Final | 8/17/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 8/19/2022 | OK to Issue CofO | RAFAEL CORTES |