8443 N CALVIN AVE 91324

Certificate Information: 8443 N CALVIN AVE 91324

Application / Permit
20010-20000-00437
Plan Check / Job No.
B20VN02312
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW(24'-0"x 49'-3") DETACHED ACCESSORY DWELLING UNIT. WORK PER ENGINEER.
Permit Issued
Issued on 7/15/2020
Issuing Office
Current Status
CofO Issued on 12/10/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2020 APPLICANT
Green Plans Picked Up 3/17/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 TROY DEGUZMAN
Corrections Issued 3/20/2020 TROY DEGUZMAN
Quality Review Completed 3/23/2020 CHON CHIO KUO
Building Plans Picked Up 3/24/2020 APPLICANT
Applicant returned to address corrections 7/10/2020 TROY DEGUZMAN
Plan Check Approved 7/15/2020 TROY DEGUZMAN
Issued 7/15/2020 APPLICANT
CofO in Progress 12/4/2020 JEFFREY PARD
CofO Issued 12/10/2020 JOHN JANSON
Permit Finaled 12/10/2020 JOHN JANSON

Permit Application Clearance Information

Green Code Cleared 4/2/2020 AARON COSTA
Address approval Cleared 4/7/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 4/7/2020 ROBERT DUFF
Eng Process Fee Ord 176,300 Cleared 4/20/2020 LEE GUILBEAUX
Sewer availability Cleared 4/20/2020 LEE GUILBEAUX
Low Impact Development Cleared 7/7/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 7/14/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/20/2020 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 7/24/2020 Corrections Issued JEFFREY PARD
BUILDING-Rough-Frame 8/14/2020 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Approved JEFFREY PARD
Green Building Rough 8/14/2020 Not Ready for Inspection JEFFREY PARD
Verify Sprinkler Sign Off 8/14/2020 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 8/25/2020 Partial Approval JEFFREY PARD
Green Building Rough 8/25/2020 Not Ready for Inspection JEFFREY PARD
Verify Sprinkler Sign Off 8/25/2020 Approved JEFFREY PARD
Deputy Drilled-In Anchors 8/27/2020 Approved JEFFREY PARD
ELECTRICAL-Rough 8/28/2020 Approved JEFFREY PARD
HVAC-Rough 8/28/2020 Approved JEFFREY PARD
PLUMBING-Rough 8/28/2020 Approved JEFFREY PARD
BUILDING-Rough-Frame 9/2/2020 Approved JEFFREY PARD
Green Building Rough 9/2/2020 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 9/2/2020 Approved JEFFREY PARD
Insulation 9/4/2020 Approved JEFFREY PARD
Drywall Nailing 9/9/2020 Approved JEFFREY PARD
Green Building Rough 9/9/2020 Approved JEFFREY PARD
Sewer 10/6/2020 Approved JEFFREY PARD
Gas Test 10/14/2020 Approved DONALD SUNSERI
ELECTRICAL-Final 10/29/2020 Approved JEFFREY PARD
Final 10/29/2020 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 10/29/2020 Approved JEFFREY PARD
Green Building Final 10/29/2020 Corrections Issued JEFFREY PARD
HVAC-Final 10/29/2020 Approved JEFFREY PARD
PLUMBING-Final 10/29/2020 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 10/29/2020 SGSOV Approved JEFFREY PARD
Service/Power Release 10/29/2020 Not Ready for Inspection JEFFREY PARD
Smoke Detectors 10/29/2020 Approved JEFFREY PARD
Final 11/18/2020 Not Ready for Inspection JEFFREY PARD
Green Building Final 11/18/2020 Approved JEFFREY PARD
Service/Power Release 11/18/2020 Not Ready for Inspection JEFFREY PARD
Final 12/3/2020 OK to Issue CofO JEFFREY PARD
Service/Power Release 12/3/2020 Approved JEFFREY PARD