479 S LORING AVE 90024

Certificate Information: 479 S LORING AVE 90024

Application / Permit
20010-20000-00431
Plan Check / Job No.
B20VN02274
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW (17'-0"x 13'-6") DETACHED ONE STORY RECREATION ROOM. WORK PER ENGINEER.
Permit Issued
Issued on 6/23/2020
Issuing Office
Current Status
CofO Issued on 4/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2020 APPLICANT
Green Plans Picked Up 2/25/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 TROY DEGUZMAN
Corrections Issued 2/29/2020 TROY DEGUZMAN
Quality Review Completed 3/5/2020 CHON CHIO KUO
Building Plans Picked Up 3/5/2020 APPLICANT
Applicant returned to address corrections 4/1/2020 TROY DEGUZMAN
Applicant returned to address corrections 4/15/2020 TROY DEGUZMAN
Plan Check Approved 6/4/2020 TROY DEGUZMAN
Applicant returned to address corrections 6/5/2020 TROY DEGUZMAN
No Progress 6/5/2020 TROY DEGUZMAN
Plan Check Approved 6/23/2020 TROY DEGUZMAN
Issued 6/23/2020 APPLICANT
CofO in Progress 4/8/2022 MICHAEL PELHAM
Permit Finaled 4/8/2022 DANIEL ORRANTE
CofO Issued 4/8/2022 DANIEL ORRANTE
Permit Finaled 4/8/2022 DANIEL ORRANTE

Permit Application Clearance Information

CPC Cleared 3/10/2020 NOAH MCCOY
GPI Written Notices Cleared 4/1/2020 TROY DEGUZMAN
Grading Pre-Inspection Cleared 4/1/2020 TROY DEGUZMAN
Eng Process Fee Ord 176,300 Cleared 4/21/2020 ANTHONY MAINEZ
Sewer availability Cleared 4/21/2020 ANTHONY MAINEZ
Green Code Cleared 4/28/2020 AARON COSTA
Low Impact Development Cleared 6/12/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 6/23/2020 DINAH GARIN

Contact Information

Contractor Blue Label Construction Inc; Lic. No.: 972011-B 1448 15TH STREET #102      SANTA MONICA, CA 90404
Engineer Tani,, Jason Yukio; Lic. No.: C58271 5296 VIA PATRICIA      THOUSAND OAKS, CA 91320

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/11/2020 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 8/24/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 8/31/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 9/11/2020 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 12/11/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 12/14/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 12/23/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 1/7/2021 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 2/3/2021 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 2/3/2021 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 2/3/2021 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 2/3/2021 Approved GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 2/3/2021 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 2/10/2021 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 3/1/2021 Approved KEVIN SARGSYAN
Final 11/3/2021 Conditional Approval BRENDAN LOONEY
Green Building Final 11/3/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 11/3/2021 SGSOV Approved BRENDAN LOONEY
Service/Power Release 11/3/2021 Approved BRENDAN LOONEY
Smoke Detectors 11/3/2021 Approved BRENDAN LOONEY
Special/Order Compliance 11/8/2021 Corrections Issued MICHAEL PELHAM
Final 11/24/2021 Conditional Approval BRENDAN LOONEY