14260 W SAYRE ST 91342

Certificate Information: 14260 W SAYRE ST 91342

Application / Permit
20010-20000-00420
Plan Check / Job No.
B20VN02217
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) TYPE V-A IRREGULAR SHAPED 29'-7" X 32'-6" ONE STORY ACCESSORY DWELLING UNIT ALL WORK PER WFPP
Permit Issued
Issued on 10/20/2020
Issuing Office
Valley
Current Status
CofO Corrected on 9/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 3/4/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 3/4/2020 OMID HEDAYAT
Building Plans Picked Up 3/4/2020 APPLICANT
Green Plans Picked Up 8/14/2020 APPLICANT
Plan Check Approved 10/6/2020 SEWADA ZADOORAN MILAGARDI
Issued 10/20/2020 APPLICANT
CofO in Progress 7/1/2022 ARAM AVEDISIAN
CofO Issued-Status Void 7/16/2022 MICHAEL SMITH
Permit Finaled-Status Void 7/16/2022 MICHAEL SMITH
Re-Activate Permit 9/8/2022 MICHAEL SMITH
Permit Finaled 9/8/2022 MICHAEL SMITH
CofO Corrected 9/8/2022 MICHAEL SMITH
Permit Finaled 9/8/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/6/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/6/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/6/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 6/26/2020 MATTHEW CRAIG
Low Impact Development Cleared 7/29/2020 SARAH YOUSSEF
Green Code Cleared 8/3/2020 MICHAEL AYERS
Roof/Waste drainage to street Cleared 8/4/2020 ADRIAN CASTRO

Contact Information

Contractor D H Property Maintenance Inc; Lic. No.: 985811-B 11312 COVELLO STREET      SUN VALLEY, CA 91352

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/10/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 2/19/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 2/25/2021 Conditional Approval MISAEL ESPARZA
Underground Mechanical 4/26/2021 Corrections Issued MISAEL ESPARZA
Gas Test 5/18/2021 Partial Approval MISAEL ESPARZA
Underground Mechanical 5/18/2021 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/11/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 6/28/2021 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/28/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 6/28/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 6/28/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/29/2021 Corrections Issued JOHN HAYES
Green Building Rough 6/29/2021 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 6/29/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/2/2021 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 7/2/2021 Approved MICHEL ABAJAN
Green Building Rough 7/2/2021 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 7/2/2021 Approved MICHEL ABAJAN
Insulation 7/8/2021 Conditional Approval MISAEL ESPARZA
Drywall Nailing 7/20/2021 Not Ready for Inspection DEANDRE HOFFMAN
Interior/Exterior Lathing 7/20/2021 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 7/26/2021 Conditional Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 7/26/2021 Conditional Approval CHRISTOPHER DELLEFIELD
HVAC-Rough 7/26/2021 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/29/2021 Approved MARK JOHNSON
Drywall Nailing 7/29/2021 Approved MARK JOHNSON
HVAC-Rough 7/29/2021 Approved MARK JOHNSON
SUSMP-Std. Urban Storm Water 5/20/2022 Approved JOHN HAYES
Final 6/2/2022 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 6/2/2022 Approved JOHN HAYES
Green Building Final 6/2/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 6/2/2022 SGSOV Not Ready JOHN HAYES
Service/Power Release 6/2/2022 Not Ready for Inspection JOHN HAYES
Smoke Detectors 6/2/2022 Not Ready for Inspection JOHN HAYES
Final 7/1/2022 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 7/1/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 7/1/2022 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 7/1/2022 Approved ARAM AVEDISIAN
Smoke Detectors 7/1/2022 Approved ARAM AVEDISIAN