7766 N CHERRYSTONE AVE 91402
Certificate Information: 7766 N CHERRYSTONE AVE 91402
- Application / Permit
- 20010-20000-00419
- Plan Check / Job No.
- B20VN02205
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ACCESSORY DWELLING UNIT ( 25'-0"x24'-0") PER LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 12/9/2020
- Issuing Office
- Current Status
- CofO Issued on 6/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | MOHAMMAD ESMAILI |
| Green Plans Picked Up | 2/28/2020 | APPLICANT |
| Corrections Issued | 2/29/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 3/2/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 3/9/2020 | APPLICANT |
| Applicant returned to address corrections | 8/14/2020 | MOHAMMAD ESMAILI |
| Plan Check Approved | 12/9/2020 | MOHAMMAD ESMAILI |
| Issued | 12/9/2020 | APPLICANT |
| CofO in Progress | 3/30/2022 | GREGG CUMMINGS |
| Permit Finaled | 6/13/2022 | DANIEL ORRANTE |
| CofO Issued | 6/13/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/13/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 3/11/2020 | GEORGE SUCHAND |
| Sewer availability | Cleared | 3/11/2020 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 3/13/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/8/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/11/2020 | ADRIAN CASTRO |
| Green Code | Cleared | 7/7/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/15/2021 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 3/15/2021 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 3/15/2021 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 3/24/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/14/2021 | No Access for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/21/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 4/21/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 4/21/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/29/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/29/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 4/29/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 4/29/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 5/7/2021 | Approved | MORRIS JACKSON |
| Pre-Inspection | 5/7/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/17/2021 | Not Ready for Inspection | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 5/18/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 5/18/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 5/18/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/3/2021 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/3/2021 | Not Ready for Inspection | DAVID MATSON |
| Pre-Inspection | 7/2/2021 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/12/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 7/12/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/13/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 7/13/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 7/13/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/27/2021 | No Access for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/27/2021 | No Access for Inspection | GREGG CUMMINGS |
| Green Building Rough | 7/27/2021 | No Access for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 7/27/2021 | No Access for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 7/27/2021 | No Access for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/11/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 8/11/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 8/11/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 9/2/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/28/2021 | Partial Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/28/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 9/28/2021 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 9/28/2021 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 9/28/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/4/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 10/4/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/7/2021 | No Access for Inspection | GREGG CUMMINGS |
| Green Building Rough | 10/7/2021 | No Access for Inspection | GREGG CUMMINGS |
| Insulation | 10/7/2021 | No Access for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/12/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 10/12/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 10/18/2021 | No Access for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/18/2021 | No Access for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 10/18/2021 | No Access for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/25/2021 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 10/25/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 10/25/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 10/25/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/25/2021 | Approved | GREGG CUMMINGS |
| Final | 11/24/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 11/24/2021 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/24/2021 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 11/24/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 11/24/2021 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 2/2/2022 | No Access for Inspection | GREGG CUMMINGS |
| HVAC-Final | 2/2/2022 | No Access for Inspection | GREGG CUMMINGS |
| Final | 2/10/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 2/10/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/10/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 2/10/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 2/10/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 2/23/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 2/23/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/23/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 2/23/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 2/23/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/14/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 3/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/14/2022 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 3/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 3/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/23/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 3/23/2022 | Approved | GREGG CUMMINGS |
| Service/Power Release | 3/23/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 3/23/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 3/30/2022 | Approved | GREGG CUMMINGS |
| Final | 3/30/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 3/30/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 3/30/2022 | Approved | GREGG CUMMINGS |
| Service/Power Release | 3/30/2022 | Approved | GREGG CUMMINGS |