927 E 25TH ST #1-17 90011

Certificate Information: 927 E 25TH ST #1-17 90011

Application / Permit
20010-20000-00364
Plan Check / Job No.
B20VN01901
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 3-STORY 17-UNITS TYPE V-A APARTMENT BLDG (100% AFFORDABLE HOUSING TOC TIER 4 & AB 744 FOR PARKING REQMT'S) [NFPA-13 FIRE SPRINKLERS THROUGHOUT]
Permit Issued
Issued on 7/19/2022
Issuing Office
Current Status
CofO Issued on 7/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2020 APPLICANT
Green Plans Picked Up 3/5/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 RODNEY SAMIIAN
Disabled Access Plans Picked Up 3/12/2020 APPLICANT
Corrections Issued 3/19/2020 RODNEY SAMIIAN
Quality Review Completed 3/19/2020 ABDUL CHEGENI
Building Plans Picked Up 3/25/2020 APPLICANT
Applicant returned to address corrections 6/8/2022 NILOOFAR MEHRAIN
Plan Check Approved 7/1/2022 NILOOFAR MEHRAIN
Issued 7/19/2022 APPLICANT
TCO Issued (Expire Date: 11-25-2024) 5/29/2024 ERNESTO CORRAL
CofO in Progress 7/8/2024 JAMES POWERS
CofO in Progress 7/8/2024 JAMES POWERS
CofO in Progress 7/10/2024 JAMES POWERS
CofO Issued 7/11/2024 ERNESTO CORRAL
Permit Finaled 7/11/2024 ERNESTO CORRAL

Permit Application Clearance Information

Permit Cleared 5/13/2020 WALLIE JONG
Address approval Cleared 5/18/2020 WALLIE JONG
CPC Cleared 5/18/2020 KENTON TRINH
Eng Process Fee Ord 176,300 Cleared 5/20/2020 WALLIE JONG
Sewer availability Cleared 6/2/2020 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 6/16/2020 JASON CHAN
Opn space landscape/Water mgmt Cleared 6/16/2020 JASON CHAN
ZA Case Cleared 6/16/2020 JASON CHAN
ZI Cleared 6/16/2020 JASON CHAN
ZI Cleared 6/16/2020 JASON CHAN
Highway dedication Cleared 7/7/2020 JAMES MORALEZ
Hydrant and Access approval Cleared 7/21/2020 KURT CORRAL
Fire Marshall Fire Life Safety Cleared 8/13/2020 VIDAL GARCIA
Density Bonus 12.22.A.31 Cleared 10/21/2020 DORIS KWOK
Low Impact Development Cleared 11/19/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/6/2021 WALLIE JONG
DAS Clearance Cleared 4/5/2022 RODNEY SAMIIAN
Green Code Cleared 4/14/2022 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/29/2022 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 10/5/2022 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 10/18/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/28/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 11/22/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Partial Approval JAMES POWERS
Green Building Rough 11/22/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 11/22/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 11/22/2022 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 12/20/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 1/25/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 1/30/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/21/2023 Partial Approval JAMES POWERS
Insulation 2/21/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 2/22/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/8/2023 Approved JAMES POWERS
Pre-Inspection 5/8/2023 Partial Approval JAMES POWERS
Insulation 5/31/2023 Approved RAFAEL ESPINOZA
Drywall Nailing 7/12/2023 Approved JAMES POWERS
Green Building Rough 7/12/2023 Approved JAMES POWERS
Final 3/6/2024 Not Ready for Inspection JAMES POWERS
Final 5/28/2024 OK for TCO JAMES POWERS
Footing/Foundation/Slab 5/28/2024 Approved JAMES POWERS
Green Building Final 5/28/2024 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV Approved JAMES POWERS
Smoke Detectors 5/28/2024 Approved JAMES POWERS
Verify Sprinkler Sign Off 5/28/2024 Approved JAMES POWERS
Wood Frame 5/28/2024 Approved JAMES POWERS
Final 7/5/2024 OK to Issue CofO JAMES POWERS