13609 W MUSCATINE ST 91331
Certificate Information: 13609 W MUSCATINE ST 91331
- Application / Permit
- 20010-20000-00356
- Plan Check / Job No.
- B20VN01808
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 23'-2" x 32'-9" TWO-STORY ACCESSORY DWELLING UNIT W/ ATTACHED COVERED PATIO
- Permit Issued
- Issued on 10/14/2020
- Issuing Office
- Current Status
- CofO Issued on 6/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | SEAN SHAHMIRI |
| Corrections Issued | 3/18/2020 | SEAN SHAHMIRI |
| Green Plans Picked Up | 3/24/2020 | APPLICANT |
| Quality Review Completed | 3/27/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 3/31/2020 | APPLICANT |
| Applicant returned to address corrections | 9/30/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 9/30/2020 | SEAN SHAHMIRI |
| Issued | 10/14/2020 | APPLICANT |
| CofO in Progress | 4/12/2022 | GREGG CUMMINGS |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
| CofO Issued | 6/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/16/2020 | RIDWAN HARDY |
| Address approval | Cleared | 6/19/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 6/22/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 8/25/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/10/2020 | ANDRES COVARRUBIAS |
| Green Code | Cleared | 9/14/2020 | DAVID MATSON |
| Roof/Waste drainage to street | Cleared | 9/29/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/2/2021 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 3/2/2021 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/10/2021 | Approved | GREGG CUMMINGS |
| Wood Frame | 5/4/2021 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2021 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 6/17/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 6/17/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/7/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 7/7/2021 | Approved | GREGG CUMMINGS |
| Wood Frame | 7/12/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/19/2021 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 7/19/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/19/2021 | Partial Approval | GREGG CUMMINGS |
| Insulation | 8/18/2021 | Conditional Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/24/2021 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 8/24/2021 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 8/30/2021 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/21/2021 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 9/22/2021 | Approved | GREGG CUMMINGS |
| Sewer | 10/6/2021 | Approved | WILLIAM WREN |
| Service/Power Release | 12/1/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 2/16/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 2/16/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/16/2022 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 2/16/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 2/16/2022 | Approved | GREGG CUMMINGS |
| Final | 3/3/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 3/3/2022 | Approved | GREGG CUMMINGS |
| Service/Power Release | 3/3/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 4/8/2022 | Corrections Issued | GREGG CUMMINGS |
| Service/Power Release | 4/8/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/12/2022 | Approved | GREGG CUMMINGS |
| Final | 4/12/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 4/12/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 4/12/2022 | Approved | GREGG CUMMINGS |
| Service/Power Release | 4/12/2022 | Approved | GREGG CUMMINGS |
| Service/Power Release | 4/13/2022 | Partial Inspection | JOHN HAYES |