15067 W ORO GRANDE ST 91342

Certificate Information: 15067 W ORO GRANDE ST 91342

Application / Permit
20010-20000-00342
Plan Check / Job No.
B20VN01742
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 46' X 26' ONE STORY ACCESSORY DWELLING UNIT WITH ATTACHED 20' X 20' GARAGE PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/1/2021
Issuing Office
Current Status
CofO Issued on 11/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2020 APPLICANT
Green Plans Picked Up 2/12/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 2/24/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 2/27/2020 OMID HEDAYAT
Building Plans Picked Up 3/9/2020 APPLICANT
Plan Check Approved 9/1/2021 SEWADA ZADOORAN MILAGARDI
Issued 9/1/2021 APPLICANT
CofO in Progress 10/24/2024 JENNIFER RABUCHIN
CofO Issued 11/14/2024 DANIEL ORRANTE
Permit Finaled 11/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

Green Code Cleared 8/25/2020 SEWADA ZADOORAN MILAGARDI
Grading Pre-Inspection Cleared 9/9/2020 PATRICK MISCHLICH
Address approval Cleared 9/25/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 10/1/2020 GABRIEL ROBLES
Sewer availability Cleared 10/1/2020 GABRIEL ROBLES
Construction near power lines Cleared 11/10/2020 RIDWAN HARDY
Low Impact Development Cleared 2/2/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/4/2021 ADRIAN CASTRO
GPI Written Notices Cleared 8/16/2021 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/28/2021 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 9/28/2021 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 10/4/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/23/2022 Partial Inspection JENNIFER RABUCHIN
Green Building Rough 2/23/2022 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 2/23/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Partial Approval JENNIFER RABUCHIN
Green Building Rough 3/4/2022 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/22/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 6/22/2022 Approved JENNIFER RABUCHIN
Gas Test 6/22/2022 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 6/22/2022 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 6/22/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/22/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/30/2022 Approved JOHN KIDWELL
Green Building Rough 6/30/2022 Approved JOHN KIDWELL
HVAC-Rough 6/30/2022 Approved JOHN KIDWELL
Insulation 7/21/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/8/2022 Approved JENNIFER RABUCHIN
Shower Pan 8/8/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 11/7/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Sewer 11/17/2022 Approved JENNIFER RABUCHIN
Underground Mechanical 11/17/2022 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 12/19/2022 Approved JENNIFER RABUCHIN
Green Building Final 7/26/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/7/2024 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 3/13/2024 Approved JENNIFER RABUCHIN
Final 3/13/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/13/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/13/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 3/13/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 3/13/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/24/2024 Approved JENNIFER RABUCHIN
Final 10/24/2024 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 10/24/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/24/2024 Approved JENNIFER RABUCHIN
Service/Power Release 10/24/2024 Approved JENNIFER RABUCHIN