6559 N TEESDALE AVE 91606

Certificate Information: 6559 N TEESDALE AVE 91606

Application / Permit
20010-20000-00337
Plan Check / Job No.
B20VN01708
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ACCESSORY DWELLING UNIT AND AND GARAGE (35'-1"x32'-0")
Permit Issued
Issued on 8/7/2020
Issuing Office
Current Status
CofO Issued on 4/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 MOHAMMAD ESMAILI
Corrections Issued 3/13/2020 MOHAMMAD ESMAILI
Green Plans Picked Up 3/17/2020 APPLICANT
Quality Review Completed 3/23/2020 OMID HEDAYAT
Building Plans Picked Up 3/24/2020 APPLICANT
Plan Check Approved 7/22/2020 MOHAMMAD ESMAILI
Issued 8/7/2020 APPLICANT
CofO in Progress 3/19/2021 MICHAEL SMITH
CofO Issued 4/3/2021 MICHAEL SMITH
Permit Finaled 4/3/2021 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 4/20/2020 RIDWAN HARDY
Address approval Cleared 5/20/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/20/2020 GABRIEL ROBLES
Sewer availability Cleared 5/20/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 6/2/2020 GEORGE SUCHAND
Green Code Cleared 6/11/2020 AARON COSTA
Low Impact Development Cleared 6/17/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/24/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/4/2020 Approved BRENDAN LOONEY
PLUMBING-Rough 9/16/2020 Partial Inspection MATTHEW NELSON
Wood Frame 9/16/2020 Partial Approval MATTHEW NELSON
Insulation 9/17/2020 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 9/18/2020 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 9/25/2020 Approved BRENDAN LOONEY
Deputy Wood Construction 10/6/2020 Conditional Approval BRENDAN LOONEY
Deputy Wood Construction 10/26/2020 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 10/28/2020 Approved BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 10/28/2020 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 11/12/2020 Not Ready for Inspection JOHN HAYES
Final 11/12/2020 Corrections Issued JOHN HAYES
Green Building Final 11/12/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 11/12/2020 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 11/12/2020 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 11/12/2020 SGSOV Not Ready JOHN HAYES
Service/Power Release 11/12/2020 Not Ready for Inspection JOHN HAYES
Sewer 11/12/2020 Not Ready for Inspection JOHN HAYES
Smoke Detectors 11/12/2020 Not Ready for Inspection JOHN HAYES
Underground Mechanical 11/12/2020 Corrections Issued JOHN HAYES
Verify Sprinkler Sign Off 11/12/2020 Not Ready for Inspection JOHN HAYES
Insulation 11/19/2020 Approved BRENDAN LOONEY
Sewer 11/19/2020 Approved BRENDAN LOONEY
Drywall Nailing 11/30/2020 Approved JOHN HAYES
Special/Order Compliance 11/30/2020 Order to Comply Issued JOHN HAYES
Special/Order Compliance 12/10/2020 Approved BRENDAN LOONEY
Pre-Inspection 1/25/2021 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 2/5/2021 Approved BRENDAN LOONEY
Final 2/5/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 2/5/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 2/5/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 2/5/2021 SGSOV Not Ready BRENDAN LOONEY
Service/Power Release 2/5/2021 Not Ready for Inspection BRENDAN LOONEY
Smoke Detectors 2/5/2021 Approved BRENDAN LOONEY
Verify Sprinkler Sign Off 2/5/2021 Approved BRENDAN LOONEY
Final 2/26/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 2/26/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 2/26/2021 SGSOV Not Ready BRENDAN LOONEY
Service/Power Release 2/26/2021 Not Ready for Inspection BRENDAN LOONEY
Final 3/15/2021 Conditional Approval DAVID MATSON
SGSOV-Seismic Gas S/O Valve 3/15/2021 SGSOV Approved DAVID MATSON
Service/Power Release 3/15/2021 Approved DAVID MATSON
Final 3/19/2021 OK to Issue CofO MICHAEL SMITH